00:00:00.000 --> 00:00:10.340
<v Dave Jones>This is the Amp Hour Podcast, released July 31st, 2023, episode number 641 with Toby Rock.

00:00:10.340 --> 00:00:32.560
<v Dave Jones>Welcome to the Amp Hour. I'm Dave Jones from the EEV blog.

00:00:33.460 --> 00:00:38.520
<v Chris Gammell>And my name's Toby Rob and I've been working in distribution power industry for around 14 years.

00:00:38.520 --> 00:00:41.400
<v Dave Jones>Hey Toby, thanks for joining us mate.

00:00:41.400 --> 00:00:41.460
<v Dave Jones>How are you Dave?

00:00:41.820 --> 00:00:45.160
<v Dave Jones>Good, good, good to have a fellow Aussie on the Amp Hour again.

00:00:45.580 --> 00:00:47.620
<v Chris Gammell>Yeah, I'm not too far south of you I think.

00:00:48.040 --> 00:00:49.620
<v Dave Jones>No, no, where from exactly?

00:00:50.540 --> 00:00:52.780
<v Chris Gammell>I'm just south of Wollongong there in Illawarra.

00:00:53.600 --> 00:01:01.640
<v Dave Jones>So yes, power, something both Chris and I don't know, well power distribution and big power stuff, something Chris and I don't know about.

00:01:02.000 --> 00:01:07.980
<v Dave Jones>We've had Paul Zaweda on the show before, he talked about the smart grid and all that sort of stuff.

00:01:07.980 --> 00:01:08.700
<v Dave Jones>So I'll link it in.

00:01:08.740 --> 00:01:13.480
<v Dave Jones>But you're more into like the transmission line stuff.

00:01:13.900 --> 00:01:17.660
<v Dave Jones>So tell us what your day, what's a typical day for you?

00:01:18.180 --> 00:01:23.020
<v Chris Gammell>Well, so I suppose in the last few years I've actually been sort of stuck behind a desk a bit more.

00:01:23.420 --> 00:01:28.600
<v Chris Gammell>But I'll probably try and talk about, you know, the sort of 10, 13 years before that.

00:01:28.600 --> 00:01:37.140
<v Chris Gammell>But I started with my company as an adult apprentice and basically became a linesman and what we call a fitter over here.

00:01:37.280 --> 00:01:38.980
<v Chris Gammell>It's basically just an electrician.

00:01:39.080 --> 00:01:44.480
<v Chris Gammell>But yeah, I work on the distribution network, which is basically poles and wires.

00:01:44.480 --> 00:01:51.000
<v Chris Gammell>So all those poles and all those wires that are out front of your house or maybe you've got some underground where you are.

00:01:51.980 --> 00:01:53.220
<v Dave Jones>We're completely underground.

00:01:53.360 --> 00:01:56.880
<v Dave Jones>I was going to ask about difference between underground and poles, but we'll go into that later, I think.

00:01:56.940 --> 00:01:57.260
<v Dave Jones>Sure.

00:01:57.400 --> 00:01:59.360
<v Dave Jones>Let's not just jump directly into that.

00:01:59.580 --> 00:02:05.040
<v Dave Jones>Tell us, where does power come from and how the hell does it get to us?

00:02:05.040 --> 00:02:09.320
<v Dave Jones>And what are the perils and pitfalls and stuff that we all take for granted?

00:02:09.500 --> 00:02:15.020
<v Dave Jones>Because we just design, most of us just design stuff that plugs into the power point or power from batteries, you know?

00:02:15.700 --> 00:02:21.380
<v Chris Gammell>Look, it's been around a very long time, the industry, and it's sort of a little hidden industry.

00:02:21.580 --> 00:02:25.380
<v Chris Gammell>It sort of runs in the background and you don't really know about it until something's wrong.

00:02:25.820 --> 00:02:26.180
<v Chris Gammell>Yeah.

00:02:26.260 --> 00:02:32.520
<v Chris Gammell>But, you know, in Australia we have our distribution network providers who sort of run the poles and wires business.

00:02:32.520 --> 00:02:36.200
<v Chris Gammell>And then you've got all your generators and you've got your transmission.

00:02:37.220 --> 00:02:46.220
<v Chris Gammell>And so, you know, in Australia we've got probably three or four, you know, big generators in New South Wales and they push out all our power.

00:02:46.340 --> 00:02:49.840
<v Chris Gammell>They push out around 600 or 700 megawatts a second.

00:02:50.540 --> 00:02:55.540
<v Dave Jones>Well, are you talking about the actual generators or the generating companies or the generation companies?

00:02:55.540 --> 00:03:00.960
<v Chris Gammell>They're all, there's sort of unusual ownership arrangements on a lot of them.

00:03:00.960 --> 00:03:06.900
<v Chris Gammell>But there's, you know, to provide the power for the whole state we've got to have a couple of generators.

00:03:07.100 --> 00:03:11.600
<v Chris Gammell>And we've got some big ones that are all coal-fired, steam-powered prime movers.

00:03:11.960 --> 00:03:13.500
<v Chris Gammell>And then there's, you know, a few little ones.

00:03:13.620 --> 00:03:17.380
<v Chris Gammell>There's some solar installations, some wind installations all around the place.

00:03:17.380 --> 00:03:22.840
<v Chris Gammell>But, you know, all combined they all get their power and they push it out onto the transmission network.

00:03:23.360 --> 00:03:24.380
<v Chris Gammell>And that's a separate group.

00:03:25.100 --> 00:03:30.120
<v Chris Gammell>But, you know, the generators, there's a few in the north of the state, a few in the south.

00:03:30.300 --> 00:03:31.100
<v Chris Gammell>They're scattered around.

00:03:31.780 --> 00:03:36.020
<v Chris Gammell>And they all send their power to marshalling stations or marshalling yards.

00:03:36.020 --> 00:03:46.920
<v Chris Gammell>And these big distribution centres, there's one, I think, just near St Mary's there, they all send their power directly to that distribution centre.

00:03:47.140 --> 00:03:51.120
<v Chris Gammell>And then from there, it's sent out via transmission networks.

00:03:51.320 --> 00:04:00.880
<v Chris Gammell>And that's when it gets to your, you know, the likes of Ausgrid, Endeavour Energy, Essential Energy, those three main providers for the state.

00:04:00.880 --> 00:04:08.800
<v Chris Gammell>And from there, off they go on their little 132kV towers and head out to all the zones.

00:04:08.800 --> 00:04:10.840
<v Dave Jones>Little, little, 132k is little.

00:04:11.760 --> 00:04:12.620
<v Dave Jones>And not to me.

00:04:12.620 --> 00:04:12.980
<v Dave Jones>It's funny.

00:04:13.360 --> 00:04:18.080
<v Chris Gammell>Dave, we use the term low voltage for LV up to about a thousand volts.

00:04:18.200 --> 00:04:19.680
<v Chris Gammell>So we consider that low voltage.

00:04:19.900 --> 00:04:20.420
<v Dave Jones>Right.

00:04:21.300 --> 00:04:22.500
<v Chris Gammell>And then we have our high voltage.

00:04:22.500 --> 00:04:28.800
<v Dave Jones>I think in the realm of electronics, it's officially 40 volts or 42 volts or something, isn't it?

00:04:28.800 --> 00:04:31.500
<v Dave Jones>So something like that is considered low voltage in the electronics?

00:04:31.500 --> 00:04:34.540
<v Chris Gammell>Probably touch safe, I think, maybe 50, 60 volts DC.

00:04:34.720 --> 00:04:36.240
<v Dave Jones>Yeah, something like that.

00:04:36.260 --> 00:04:36.980
<v Dave Jones>Something like that, yeah.

00:04:37.380 --> 00:04:38.920
<v Chris Gammell>Yeah, it's quite a big industry.

00:04:39.040 --> 00:04:40.580
<v Chris Gammell>And there's actually a lot that goes on.

00:04:40.700 --> 00:04:43.700
<v Chris Gammell>There's quite a bit of engineering that goes into all of it.

00:04:44.800 --> 00:04:52.200
<v Chris Gammell>Not only all the work that gets carried out in the street, all the poles and the wires that have all got to be put in, maintained and looked after.

00:04:52.200 --> 00:05:00.580
<v Chris Gammell>But there's a lot of engineers that run in the background too to design all the protection systems for the transmission and the zone subs.

00:05:01.980 --> 00:05:05.240
<v Chris Gammell>So I don't know where the best place to start is, but...

00:05:05.240 --> 00:05:05.780
<v Chris Gammell>Generation?

00:05:06.320 --> 00:05:07.340
<v Chris Gammell>Yeah, the prime movers.

00:05:07.680 --> 00:05:10.100
<v Chris Gammell>They're mostly coal driven, coal fed.

00:05:10.300 --> 00:05:18.780
<v Chris Gammell>The coal comes in usually on conveyor belts from a nearby coal mine or like a big, they have a big gathering area where they just pile up the coal.

00:05:18.780 --> 00:05:26.300
<v Chris Gammell>And there's a big, like a feeder that grabs it and crushes it, powders it and then throws it into the furnace.

00:05:27.120 --> 00:05:35.060
<v Chris Gammell>There's usually near every generator, there's usually a water source and that water's brought in and they make steam and they drive a turbine and they call that the prime mover.

00:05:35.540 --> 00:05:47.960
<v Chris Gammell>It usually pushes out around 12 kV on the rotor and they then put that into their local marshalling yard and bump it up to usually in the 330 to 500 kV range.

00:05:47.960 --> 00:05:52.340
<v Chris Gammell>And then they send it out to the various areas for splitting up.

00:05:52.680 --> 00:05:55.780
<v Dave Jones>Why does the generator only output 12 kV?

00:05:55.880 --> 00:06:00.900
<v Dave Jones>Is that just like the winding, like breaks down and stuff like that in the motors in the gen?

00:06:01.060 --> 00:06:07.760
<v Chris Gammell>So sort of, you know, high voltage machines, they're sort of hard to insulate at the best of times.

00:06:07.760 --> 00:06:08.260
<v Chris Gammell>Yeah.

00:06:08.260 --> 00:06:16.600
<v Chris Gammell>And so when you've got this big spinning generator that everyone has to work on and, you know, they take as long as three or four buses, some of these things, they take up a big whole floor.

00:06:17.720 --> 00:06:20.280
<v Chris Gammell>And yeah, they just, they sort of limit the output.

00:06:20.280 --> 00:06:27.340
<v Chris Gammell>And then, but of course, for transmission, we want that high voltage to have that low I squared R loss.

00:06:27.400 --> 00:06:29.280
<v Chris Gammell>So they push it up to the 330, 500.

00:06:30.240 --> 00:06:37.020
<v Dave Jones>And they do that straight away because you don't want to be transmitting huge power from the main generator any sort of distance.

00:06:37.120 --> 00:06:42.640
<v Dave Jones>You want to bump it up to 500 kV as fast as you can or as near to the gen as you can.

00:06:42.640 --> 00:06:48.840
<v Chris Gammell>Yeah. And they'll, yeah, they'll bump it up straight away and then send it out from there.

00:06:48.900 --> 00:06:50.660
<v Chris Gammell>And that's when Transgrid get a hold of it.

00:06:51.020 --> 00:06:53.000
<v Chris Gammell>And they'll send it out throughout the state.

00:06:53.300 --> 00:07:01.000
<v Chris Gammell>And they'll manage that sort of higher level generators coming on and off load and picking up the load.

00:07:01.080 --> 00:07:07.660
<v Chris Gammell>Because the generators, they do have a governor that holds the generator at 50 hertz.

00:07:07.660 --> 00:07:16.040
<v Chris Gammell>So as the power, you know, load increases, the throttle will open up and she'll put a bit more power in to keep that 50 hertz going.

00:07:17.040 --> 00:07:22.240
<v Dave Jones>But on average, over a long time, it's almost precisely 50 hertz.

00:07:22.400 --> 00:07:22.740
<v Dave Jones>Is that right?

00:07:22.740 --> 00:07:23.320
<v Chris Gammell>It really is, yeah.

00:07:23.460 --> 00:07:23.660
<v Chris Gammell>Yeah.

00:07:23.660 --> 00:07:24.560
<v Chris Gammell>It's very good.

00:07:24.560 --> 00:07:24.760
<v Chris Gammell>Pretty bang on.

00:07:25.360 --> 00:07:25.620
<v Chris Gammell>Yeah.

00:07:25.700 --> 00:07:31.980
<v Chris Gammell>It's actually kind of fascinating the way, you know, the synchronicity works across the network that, you know,

00:07:31.980 --> 00:07:40.160
<v Chris Gammell>the generator is spinning at 50 hertz and it's, you know, pushing and pulling that electric field right out through the neighborhoods.

00:07:40.900 --> 00:07:47.280
<v Chris Gammell>And, you know, there's three phase motors in premises and industrial processes that are all spinning at the same speed.

00:07:47.440 --> 00:07:51.080
<v Chris Gammell>And they're like a, it's like the big generator sort of divvied up its work.

00:07:51.160 --> 00:07:55.320
<v Chris Gammell>And it's all in all these other smaller machines, but they're all still running as well.

00:07:55.320 --> 00:07:58.720
<v Dave Jones>How do the different generator plants synchronize together?

00:07:58.880 --> 00:08:03.960
<v Dave Jones>Is that done via like some, you know, comms, like optical fiber network?

00:08:04.240 --> 00:08:14.680
<v Dave Jones>Or do they, well, I guess this isn't precisely your area, but, or can they just like, one of them is like the master and the others are kind of like slave and they just know?

00:08:14.680 --> 00:08:15.720
<v Chris Gammell>They're all synchronized.

00:08:15.860 --> 00:08:20.320
<v Chris Gammell>One of them could drop on and off and it wouldn't, you know, wouldn't change the others in any way.

00:08:20.320 --> 00:08:20.640
<v Chris Gammell>Yeah.

00:08:21.060 --> 00:08:27.440
<v Chris Gammell>I guess that that's why, you know, the black start would be a problem where you don't have a synchronized source.

00:08:27.820 --> 00:08:28.480
<v Dave Jones>You've got nothing.

00:08:28.640 --> 00:08:33.000
<v Dave Jones>The grid, the entire country's grid is completely down and you've got to bring it up from scratch.

00:08:33.280 --> 00:08:33.400
<v Dave Jones>Yeah.

00:08:33.540 --> 00:08:44.780
<v Chris Gammell>And that's why, you know, we've got, there's things like the hydroelectric system, which can just instantly push out, you know, about 20 or 30 megawatts straight away.

00:08:44.780 --> 00:08:49.040
<v Chris Gammell>And that's enough to supply the rotors in the big prime movers with some current.

00:08:49.040 --> 00:08:50.740
<v Dave Jones>Ah, got it.

00:08:50.840 --> 00:08:52.180
<v Dave Jones>So if you had no hydro.

00:08:52.180 --> 00:09:00.400
<v Dave Jones>So if you had no, none of that instant hydro energy, how would you start up the big gens from like nothing?

00:09:01.460 --> 00:09:07.900
<v Chris Gammell>I'm not sure they could have, I mean, it'd be pretty unlikely to have, you know, all of the generators stop working.

00:09:08.600 --> 00:09:11.660
<v Chris Gammell>The protection systems isolate all that stuff straight away.

00:09:11.660 --> 00:09:14.900
<v Chris Gammell>So that it's unlikely that they would stop completely.

00:09:15.540 --> 00:09:15.800
<v Chris Gammell>I'm sure.

00:09:15.800 --> 00:09:20.200
<v Dave Jones>What is the biggest outage we've had here in this state, New South Wales?

00:09:20.200 --> 00:09:23.860
<v Dave Jones>Because I like to me, I've, I've lived here my entire life.

00:09:23.860 --> 00:09:24.200
<v Dave Jones>Right.

00:09:24.200 --> 00:09:29.520
<v Dave Jones>So it's always been almost a hundred percent reliable.

00:09:29.520 --> 00:09:40.380
<v Dave Jones>I can count the number of blackouts like on two hands, like, and, and like they don't really last longer than like, you know, a couple of hours at absolute most.

00:09:40.380 --> 00:09:41.200
<v Chris Gammell>Yeah, no, it is really good.

00:09:41.200 --> 00:09:46.080
<v Chris Gammell>Um, obviously everyone gets their outages when there's program work, you know, you get your notification.

00:09:46.100 --> 00:09:46.760
<v Chris Gammell>Oh yeah, of course.

00:09:46.780 --> 00:09:55.020
<v Chris Gammell>They knock the power out for a day, but you know, unplanned outages, there's a fair few in the regional areas, you know, under storm or bushfire conditions.

00:09:55.020 --> 00:10:01.120
<v Chris Gammell>They're the ones that seem to cause the most outages, but, um, and then sometimes you get the cable interconnects.

00:10:01.120 --> 00:10:02.700
<v Chris Gammell>Like, I don't know if you remember that.

00:10:02.800 --> 00:10:05.460
<v Chris Gammell>I think there was one that was, um, across the harbor there.

00:10:05.560 --> 00:10:07.220
<v Chris Gammell>One of the primary cables failed.

00:10:07.380 --> 00:10:10.180
<v Chris Gammell>The secondary cable picked up the load, but it just couldn't handle it.

00:10:10.180 --> 00:10:10.660
<v Chris Gammell>And it failed.

00:10:10.660 --> 00:10:12.520
<v Chris Gammell>No, I don't, I don't remember that.

00:10:12.600 --> 00:10:13.040
<v Chris Gammell>In Sydney somewhere.

00:10:13.340 --> 00:10:18.780
<v Chris Gammell>Um, but that was, you know, and that was about a half a day or a day or two, but yeah, we're pretty fortunate here.

00:10:18.800 --> 00:10:21.380
<v Chris Gammell>We don't have long-term rolling blackouts.

00:10:21.380 --> 00:10:29.380
<v Dave Jones>Yeah, I mean, of course we had the famous one in, uh, South Australia that, that actually resulted in, that was bushfire related.

00:10:29.380 --> 00:10:32.380
<v Dave Jones>Wasn't the poles just totally collapsed or something.

00:10:32.380 --> 00:10:32.880
<v Dave Jones>Or storm related.

00:10:32.880 --> 00:10:33.380
<v Dave Jones>Yeah.

00:10:33.380 --> 00:10:33.880
<v Dave Jones>Yeah.

00:10:33.880 --> 00:10:33.880
<v Speaker ?>

00:10:33.880 --> 00:10:34.880
<v Dave Jones>Or something like that.

00:10:34.880 --> 00:10:35.380
<v Dave Jones>Yeah.

00:10:35.380 --> 00:10:39.380
<v Dave Jones>That was a huge, and that took down like, you know, a whole grid.

00:10:39.380 --> 00:10:46.380
<v Dave Jones>In fact, the, um, the control center for all of the Eastern seaboard is here, just a stone strove from my lab.

00:10:46.380 --> 00:10:48.380
<v Dave Jones>Um, and the bastards wouldn't let me in.

00:10:48.380 --> 00:10:48.380
<v Speaker ?>

00:10:48.380 --> 00:10:50.380
<v Dave Jones>Apparently that this is where they are.

00:10:50.380 --> 00:10:52.380
<v Dave Jones>This is where they control it all from.

00:10:52.380 --> 00:10:54.380
<v Dave Jones>Um, it, they don't just control this state.

00:10:54.380 --> 00:10:56.380
<v Dave Jones>Apparently they control the whole Eastern seaboard.

00:10:56.380 --> 00:10:57.380
<v Dave Jones>Okay.

00:10:57.380 --> 00:10:59.380
<v Dave Jones>Is that, that's what they told me.

00:10:59.380 --> 00:11:00.380
<v Chris Gammell>I'm not sure.

00:11:00.380 --> 00:11:04.380
<v Chris Gammell>I know that literally every, um, company has their own control rooms.

00:11:04.380 --> 00:11:08.380
<v Chris Gammell>I can only speak, the company I work for has sort of a North and a South, uh, control room.

00:11:08.380 --> 00:11:12.380
<v Chris Gammell>And, and they monitor all their incomings and outgoings.

00:11:12.380 --> 00:11:17.380
<v Chris Gammell>And, um, you know, they can switch pretty much anywhere on the network and switch around any sort of problems.

00:11:17.380 --> 00:11:25.380
<v Chris Gammell>And yeah, they do have to, I think they have to look at, you know, what the, um, potential demands going to be like.

00:11:25.380 --> 00:11:30.380
<v Chris Gammell>Like they sort of start to get, you know, really concerned on the really hot days.

00:11:30.380 --> 00:11:33.380
<v Chris Gammell>They make sure they've got a plan and they've, you know, bought enough power for the day.

00:11:33.380 --> 00:11:37.380
<v Chris Gammell>But other than that, it's, it's fairly simplistic and each of them all coordinate.

00:11:37.380 --> 00:11:50.380
<v Chris Gammell>But when there's, when there's outages that, um, you know, go between, uh, companies or between systems, that's when they have to do a bit more coordination because you might have to ask someone at the other end to do some switching for you.

00:11:50.380 --> 00:11:55.380
<v Dave Jones>You know, do we get power from other States or are we a net export?

00:11:55.380 --> 00:11:56.380
<v Dave Jones>Do you know Dave?

00:11:56.380 --> 00:11:57.380
<v Chris Gammell>I don't know.

00:11:57.380 --> 00:12:13.380
<v Chris Gammell>I'm, um, I'm not going to say I'm, um, a basic liney, but I, but I, you know, you know, there's a bit of a thing at, at, um, in, in the power industry about lineys and fitters, you know, who's the best, but, um, you know what I mean?

00:12:13.380 --> 00:12:26.380
<v Chris Gammell>But, um, out West you find they're pretty much identical roles, but in the city, you know, you've got your lineys and your fitters, but, but, um, you know, from, from a distribution network point of view, we don't see a lot of that.

00:12:26.380 --> 00:12:27.380
<v Dave Jones>Um, right.

00:12:27.380 --> 00:12:33.380
<v Chris Gammell>And because we haven't had many outages, we've never really even had to sort of deal with, deal with it, I guess.

00:12:33.380 --> 00:12:39.380
<v Dave Jones>But got it. So, so what is the highest voltage that you deal with as a line, as a linesman?

00:12:39.380 --> 00:12:44.380
<v Chris Gammell>Yeah. So, um, 132 KV is the highest network voltage for our towers.

00:12:44.380 --> 00:12:50.380
<v Chris Gammell>And that will be the same for people like Ausgrid, Endeavour Energy and, um, Essential.

00:12:50.380 --> 00:12:52.380
<v Chris Gammell>They're the New South Wales providers.

00:12:52.380 --> 00:12:58.380
<v Chris Gammell>And we'll, we'll get the power at 132 KV and that comes from Transgrid, their marshalling yards.

00:12:58.380 --> 00:13:02.380
<v Chris Gammell>And from there, they'll bring it into the zone subs.

00:13:02.380 --> 00:13:12.380
<v Chris Gammell>You, you probably see the sort of almost, um, like look like city buildings with a, um, you know, like almost like a dwelling, but a bit more industrial.

00:13:12.380 --> 00:13:15.380
<v Chris Gammell>And then they've got the gates and the big fences around them.

00:13:15.380 --> 00:13:17.380
<v Chris Gammell>Yeah. And they'll have some outdoor transformers.

00:13:17.380 --> 00:13:20.380
<v Chris Gammell>Sometimes they'll have outdoor indoor transformers.

00:13:20.380 --> 00:13:27.380
<v Chris Gammell>They're like, uh, they put walls around them, but they're open to the sky and they'll buck the one 32 down to 66 or 33.

00:13:27.380 --> 00:13:30.380
<v Dave Jones>What are those, are those walls just like fire containment?

00:13:30.380 --> 00:13:32.380
<v Dave Jones>So it doesn't spread to the rest of the facility?

00:13:32.380 --> 00:13:36.380
<v Chris Gammell>Yeah. Although, you know, touch wood, we haven't really had many of those, but yeah, things like that.

00:13:36.380 --> 00:13:40.380
<v Chris Gammell>Just also maybe visual amenity as well, because they have to be in neighbourhoods.

00:13:40.380 --> 00:13:45.380
<v Chris Gammell>Um, all of them are bunded as well to catch any spills if there's anything like that was to happen.

00:13:45.380 --> 00:13:48.380
<v Chris Gammell>So they're all, they're all pretty well maintained like that.

00:13:48.380 --> 00:13:56.380
<v Chris Gammell>Um, and, but they, they're what we call our transmissions own subs, and they don't really have any customers connected to them.

00:13:56.380 --> 00:14:05.380
<v Chris Gammell>They just take that one 32 and then they split it up to send to our other zone subs, which are the ones that are a little bit closer to town potentially.

00:14:05.380 --> 00:14:06.380
<v Dave Jones>I got it.

00:14:06.380 --> 00:14:11.380
<v Dave Jones>Okay. So we're still talking outside of may like outside of Sydney here, are we?

00:14:11.380 --> 00:14:19.380
<v Chris Gammell>Um, no, there's a, there's transmission subs. There's one in Blacktown, there's Parramatta, there's transmission subs all around the place, Hoxton Park.

00:14:19.380 --> 00:14:30.380
<v Chris Gammell>Um, but they're, they're sort of, one of those might do, you know, several suburbs or more provide those 66 kV transmission lines.

00:14:30.380 --> 00:14:32.380
<v Chris Gammell>And that's when we sort of lose the towers.

00:14:32.380 --> 00:14:34.380
<v Chris Gammell>And now we're going on to our poles.

00:14:34.380 --> 00:14:40.380
<v Dave Jones>Right. So we're talking, so it, transmission is usually 330 or 500, right?

00:14:40.380 --> 00:14:41.380
<v Dave Jones>Yeah.

00:14:41.380 --> 00:14:45.380
<v Dave Jones>Main transmission from the power stations. And then they drop, then 132 is the next level.

00:14:45.380 --> 00:14:46.380
<v Chris Gammell>That's right.

00:14:46.380 --> 00:14:47.380
<v Dave Jones>And then 60?

00:14:47.380 --> 00:14:48.380
<v Dave Jones>66.

00:14:48.380 --> 00:14:51.380
<v Dave Jones>66 is the next level after that.

00:14:51.380 --> 00:14:52.380
<v Dave Jones>Yeah.

00:14:52.380 --> 00:14:53.380
<v Chris Gammell>Okay. Got it.

00:14:53.380 --> 00:15:01.380
<v Chris Gammell>And that's when we get onto the poles. Often it'll be maybe a vertically constructed concrete pole, or maybe timber poles.

00:15:01.380 --> 00:15:07.380
<v Chris Gammell>And, um, one of the tricks with insulators, if you count the number of rings, you can kind of get a rough idea of the voltage.

00:15:07.380 --> 00:15:14.380
<v Chris Gammell>Maybe there's six, six skirts on the insulator. You're looking at 66 kV. You might see three skirts. It might be 33.

00:15:14.380 --> 00:15:20.380
<v Chris Gammell>So the, you know, from there, that's when we get to the zone subs and there'll be one of those per suburb.

00:15:20.380 --> 00:15:26.380
<v Chris Gammell>You know, there'll be one in Penrith. There'll be one in Blacktown. There'll be one for every suburb. They're quite smaller.

00:15:26.380 --> 00:15:37.380
<v Chris Gammell>And that's when we take the 66 and there might be a couple of transformers hooked up to a bar. And then from there, they'll have an output of around 11 kV.

00:15:37.380 --> 00:15:47.380
<v Chris Gammell>And that'll, that'll connect to a bar and hanging off that bar will be a number of breakers, 11 kV breakers, distribution breakers.

00:15:47.380 --> 00:16:01.380
<v Chris Gammell>And they're the ones that then go out into the streets on the poles again. And they're the ones that power up the transformers that are on the poles or the pad mount transformers that then produce our low voltage.

00:16:01.380 --> 00:16:06.380
<v Dave Jones>And which is a 240 volt, uh, three, well, the, uh, three phase.

00:16:06.380 --> 00:16:11.380
<v Dave Jones>Sorry. Yes. I'm old school. Sorry. They changed that in like the 1980s. Didn't they?

00:16:11.380 --> 00:16:15.380
<v Chris Gammell>It's a bit silly. It's, uh, I think we're trying to align with the rest of the world.

00:16:15.380 --> 00:16:22.380
<v Chris Gammell>It's, it's plus 10% minus six. So two 53 to two 17, I think something around there.

00:16:22.380 --> 00:16:28.380
<v Chris Gammell>The point of it is, um, is that, um, you know, some people are bringing their two 20 volts up to two 30.

00:16:28.380 --> 00:16:32.380
<v Chris Gammell>We're bringing our two 40 down to two 30 half of that, the one 15s.

00:16:32.380 --> 00:16:36.380
<v Chris Gammell>Some of the one 10 countries are coming up to one 15 and so on.

00:16:36.380 --> 00:16:39.380
<v Chris Gammell>Okay. So I think, I think there's some alignment there.

00:16:39.380 --> 00:16:42.380
<v Chris Gammell>They're just, obviously it makes sense to, you know,

00:16:42.380 --> 00:16:45.380
<v Chris Gammell>minimize the number of voltages in equipment around the world.

00:16:45.380 --> 00:16:46.380
<v Dave Jones>Yeah, of course.

00:16:46.380 --> 00:16:50.380
<v Dave Jones>Who, who makes the trend? Like who makes the transformers?

00:16:50.380 --> 00:16:53.380
<v Dave Jones>Is there like one company that special? I know there's lots.

00:16:53.380 --> 00:16:58.380
<v Chris Gammell>Lots, lots. Um, so our friend Chris ABB, I believe they make a lot of

00:16:58.380 --> 00:17:05.380
<v Chris Gammell>really good, lots of gear. Uh, they make a lot of switch gear and transformers, but, um, you know,

00:17:05.380 --> 00:17:11.380
<v Chris Gammell>they've been over the years, there's been various manufacturers, um, you know, contribute some of the

00:17:11.380 --> 00:17:14.380
<v Chris Gammell>transformers like a one 32 to 66 KV.

00:17:14.380 --> 00:17:18.380
<v Chris Gammell>You might need a one year lead time to get something like that.

00:17:18.380 --> 00:17:19.380
<v Dave Jones>Oh, okay.

00:17:19.380 --> 00:17:20.380
<v Dave Jones>Potentially.

00:17:20.380 --> 00:17:25.380
<v Chris Gammell>And you may need to get it shipped on a truck that will block three or four roads.

00:17:25.380 --> 00:17:26.380
<v Chris Gammell>You know, three, four.

00:17:26.380 --> 00:17:28.380
<v Chris Gammell>I've got a video of one of those.

00:17:28.380 --> 00:17:30.380
<v Dave Jones>I, yeah, I actually haven't uploaded it yet.

00:17:30.380 --> 00:17:32.380
<v Dave Jones>I've, yeah, I'll put it on my second channel.

00:17:32.380 --> 00:17:34.380
<v Dave Jones>We, I was just going in there.

00:17:34.380 --> 00:17:37.380
<v Dave Jones>I was just driving through the outback and we had to pull off to the side of the road.

00:17:37.380 --> 00:17:39.380
<v Dave Jones>The cops came past, waving everyone off.

00:17:39.380 --> 00:17:44.380
<v Dave Jones>Here comes this huge truck with this massive ass transformer hanging over the sides of the truck,

00:17:44.380 --> 00:17:47.380
<v Dave Jones>you know, so they had to shut down the whole highway.

00:17:47.380 --> 00:17:48.380
<v Chris Gammell>Yeah.

00:17:48.380 --> 00:17:49.380
<v Dave Jones>Just, uh, yeah.

00:17:49.380 --> 00:17:54.380
<v Chris Gammell>A lot of those own subs will have anything from sort of one to four or five or six transformers

00:17:54.380 --> 00:17:55.380
<v Chris Gammell>potentially.

00:17:55.380 --> 00:18:01.380
<v Chris Gammell>Um, do you want to talk a bit about the arrangement of the transformers and the way they are connected?

00:18:01.380 --> 00:18:02.380
<v Chris Gammell>Yeah, we can definitely do that.

00:18:02.380 --> 00:18:08.380
<v Dave Jones>I I've just got one question about, before I forget about the, um, industrial business parks

00:18:08.380 --> 00:18:14.380
<v Dave Jones>like I'm in, um, are they, are they treated any differently power wise to like a regular suburban

00:18:14.380 --> 00:18:15.380
<v Dave Jones>suburb?

00:18:15.380 --> 00:18:16.380
<v Dave Jones>Yeah, a little actually.

00:18:16.380 --> 00:18:17.380
<v Dave Jones>I assume they'd use more.

00:18:17.380 --> 00:18:18.380
<v Chris Gammell>Yeah, they do.

00:18:18.380 --> 00:18:22.380
<v Chris Gammell>And so, um, a lot of them, they're what we call, um, HVCs, high voltage customers.

00:18:22.380 --> 00:18:29.380
<v Chris Gammell>And some of them will take the, take the, um, power straight from, uh, the company at, at 11 KV.

00:18:29.380 --> 00:18:31.380
<v Chris Gammell>And they'll have their own transformers.

00:18:31.380 --> 00:18:32.380
<v Dave Jones>Yeah.

00:18:32.380 --> 00:18:37.380
<v Dave Jones>Cause my, uh, building, my, my building here has like a massive room that powers this entire

00:18:37.380 --> 00:18:38.380
<v Dave Jones>building.

00:18:38.380 --> 00:18:40.380
<v Dave Jones>And I assume that's 11 KV.

00:18:40.380 --> 00:18:41.380
<v Chris Gammell>Yeah.

00:18:41.380 --> 00:18:42.380
<v Chris Gammell>You'll see, you'll see them.

00:18:42.380 --> 00:18:46.380
<v Chris Gammell>They'll have, you know, warning electricity and there'll be a locked door, um, maybe vented

00:18:46.380 --> 00:18:47.380
<v Chris Gammell>and things like that.

00:18:47.380 --> 00:18:51.380
<v Chris Gammell>And, um, yeah, they'll have an indoor transformer.

00:18:51.380 --> 00:18:52.380
<v Chris Gammell>That's a ground level.

00:18:52.380 --> 00:18:53.380
<v Chris Gammell>Yep.

00:18:53.380 --> 00:18:54.380
<v Chris Gammell>Yep.

00:18:54.380 --> 00:18:56.380
<v Chris Gammell>So a little bit, a little bit tricky to work with and manage, you know, because it's right

00:18:56.380 --> 00:18:57.380
<v Chris Gammell>there at ground level.

00:18:57.380 --> 00:18:58.380
<v Chris Gammell>Um, right.

00:18:58.380 --> 00:19:02.380
<v Dave Jones>Oh, maybe you're the guy to give us a guided tour of a room like that.

00:19:02.380 --> 00:19:03.380
<v Dave Jones>Would that be your area?

00:19:03.380 --> 00:19:08.380
<v Chris Gammell>I would love to, to somehow get you a tour of one of our nice new zone subs.

00:19:08.380 --> 00:19:10.380
<v Chris Gammell>Um, I might have to try to ask around for you.

00:19:10.380 --> 00:19:12.380
<v Chris Gammell>No, I'm talking about my building here.

00:19:12.380 --> 00:19:13.380
<v Dave Jones>Oh, okay.

00:19:13.380 --> 00:19:16.380
<v Dave Jones>I'm talking about my building cause I can get access to the room.

00:19:16.380 --> 00:19:17.380
<v Dave Jones>So.

00:19:17.380 --> 00:19:22.380
<v Chris Gammell>You need to, you need to, um, wait for someone that's, you probably won't get access to the room.

00:19:22.380 --> 00:19:24.380
<v Chris Gammell>Probably won't get access to the transformer room.

00:19:24.380 --> 00:19:25.380
<v Chris Gammell>Right.

00:19:25.380 --> 00:19:26.380
<v Chris Gammell>It definitely will be keyed.

00:19:26.380 --> 00:19:27.380
<v Chris Gammell>Yeah.

00:19:27.380 --> 00:19:30.380
<v Chris Gammell>That's, but like you say, they do, they have a transformer room.

00:19:30.380 --> 00:19:34.380
<v Chris Gammell>Sometimes they might have a couple of the green pad mount boxes just out the front and

00:19:34.380 --> 00:19:38.380
<v Chris Gammell>they'll have, you know, low voltage cable, quite heavy duty cable running into the building

00:19:38.380 --> 00:19:41.380
<v Chris Gammell>and they'll have their own switch gear in there and their own protection distribution

00:19:41.380 --> 00:19:42.380
<v Chris Gammell>boards.

00:19:42.380 --> 00:19:44.380
<v Chris Gammell>But yeah, a lot of them do.

00:19:44.380 --> 00:19:45.380
<v Chris Gammell>They have an indoor transformer.

00:19:45.380 --> 00:19:46.380
<v Chris Gammell>Yep.

00:19:46.380 --> 00:19:47.380
<v Dave Jones>Right.

00:19:47.380 --> 00:19:48.380
<v Dave Jones>Interesting.

00:19:48.380 --> 00:19:52.360
<v Dave Jones>So how, like, do you have problems with like the government say, oh, I'm

00:19:52.360 --> 00:19:53.360
<v Dave Jones>like, oh, we're building a new suburb.

00:19:53.360 --> 00:19:54.360
<v Dave Jones>Boom.

00:19:54.360 --> 00:19:55.360
<v Dave Jones>Right here.

00:19:55.360 --> 00:19:56.360
<v Dave Jones>And we want to get it done.

00:19:56.360 --> 00:20:00.360
<v Dave Jones>You guys go, uh, uh, sorry, we don't have the spare power available.

00:20:00.360 --> 00:20:03.360
<v Dave Jones>Is that a, cause I, I know that happens with sewage.

00:20:03.360 --> 00:20:07.360
<v Dave Jones>I know that happens with like sewage and water and stuff.

00:20:07.360 --> 00:20:09.360
<v Dave Jones>It's like the government says, we're going to install a new suburb.

00:20:09.360 --> 00:20:13.360
<v Dave Jones>And then the authorities go, no, sorry, we don't have the excess.

00:20:13.360 --> 00:20:14.360
<v Chris Gammell>Yeah.

00:20:14.360 --> 00:20:18.360
<v Chris Gammell>No one wants to get told second, but they, they generally have to apply.

00:20:18.360 --> 00:20:24.360
<v Chris Gammell>I think for a certain size of connected load, you, you must advise the distribution provider

00:20:24.360 --> 00:20:25.360
<v Chris Gammell>that you intend to do it.

00:20:25.360 --> 00:20:29.360
<v Chris Gammell>And they'll take a look at the infrastructure that they have in the area.

00:20:29.360 --> 00:20:34.360
<v Chris Gammell>And then there's a little conversation around how it's going to be provided below a certain

00:20:34.360 --> 00:20:39.360
<v Chris Gammell>amount though, your average person with a house, not really something you have to talk to them

00:20:39.360 --> 00:20:40.360
<v Chris Gammell>about.

00:20:40.360 --> 00:20:43.360
<v Dave Jones>They've got that capacity, but yeah, of course, but an entire suburb, if the government says,

00:20:43.360 --> 00:20:45.360
<v Dave Jones>well, we're going to plug a new suburb here.

00:20:45.360 --> 00:20:46.360
<v Dave Jones>Like a suburb takes a lot of room.

00:20:46.360 --> 00:20:50.360
<v Chris Gammell>There's been a lot of building lately around the airport sites and everywhere else.

00:20:50.360 --> 00:20:53.360
<v Chris Gammell>And, and, and yeah, it is, it's planned well in advance.

00:20:53.360 --> 00:20:56.360
<v Dave Jones>Now getting back to, sorry, we've got sidetracked.

00:20:56.360 --> 00:20:57.360
<v Dave Jones>What were you going to talk about the.

00:20:57.360 --> 00:21:02.360
<v Chris Gammell>Oh, just, just the trans the way the transformers are hooked up is it's really interesting.

00:21:02.360 --> 00:21:07.360
<v Chris Gammell>They, the, the inputs generally come in and the outputs, they generally come into what's

00:21:07.360 --> 00:21:08.360
<v Chris Gammell>called a bar.

00:21:08.360 --> 00:21:11.360
<v Chris Gammell>It's just basically a bar, a metal bar.

00:21:11.360 --> 00:21:12.360
<v Dave Jones>Okay.

00:21:12.360 --> 00:21:13.360
<v Dave Jones>It's physically a bus bar.

00:21:13.360 --> 00:21:14.360
<v Chris Gammell>Yeah.

00:21:14.360 --> 00:21:15.360
<v Dave Jones>Physically a giant.

00:21:15.360 --> 00:21:16.360
<v Dave Jones>Is it copper?

00:21:16.360 --> 00:21:17.360
<v Dave Jones>It's aluminum mostly.

00:21:17.360 --> 00:21:22.360
<v Chris Gammell>Most of them are aluminum because it's lighter and it's almost as conductive.

00:21:22.360 --> 00:21:23.360
<v Chris Gammell>Yes.

00:21:23.360 --> 00:21:26.360
<v Dave Jones>And people don't know this power lines.

00:21:26.360 --> 00:21:31.360
<v Dave Jones>Please correct me if I'm wrong, but practically every power line, every street pole, every

00:21:31.360 --> 00:21:34.360
<v Dave Jones>500 kV transmission line, it is not copper.

00:21:34.360 --> 00:21:35.360
<v Chris Gammell>It is not copper.

00:21:35.360 --> 00:21:38.360
<v Chris Gammell>There are some older, older areas around Blacktown and places like that.

00:21:38.360 --> 00:21:41.360
<v Chris Gammell>You'll notice they have a green tinge that are copper, but they're pretty rare.

00:21:41.360 --> 00:21:45.360
<v Chris Gammell>You might see a streetlight conductor, which is a separate conductor underneath and that's

00:21:45.360 --> 00:21:48.360
<v Chris Gammell>often copper, but it's extremely heavy.

00:21:48.360 --> 00:21:51.360
<v Chris Gammell>I think the density is maybe eight or 12 or something.

00:21:51.360 --> 00:21:54.360
<v Chris Gammell>And, and you know, aluminum is in the two.

00:21:54.360 --> 00:21:57.360
<v Dave Jones>Oh, you mean even though it's not as good a conductor, you're willing to trade off that

00:21:57.360 --> 00:21:58.360
<v Dave Jones>force for the weight.

00:21:58.360 --> 00:21:59.360
<v Chris Gammell>It's very close.

00:21:59.360 --> 00:22:02.360
<v Chris Gammell>And you can up the size of the conductor slightly.

00:22:02.360 --> 00:22:03.360
<v Dave Jones>Right.

00:22:03.360 --> 00:22:04.360
<v Dave Jones>Yes.

00:22:04.360 --> 00:22:05.360
<v Dave Jones>Got it to compensate.

00:22:05.360 --> 00:22:06.360
<v Dave Jones>And it's still lighter than the coppler equivalent.

00:22:06.360 --> 00:22:07.360
<v Chris Gammell>It is.

00:22:07.360 --> 00:22:12.360
<v Chris Gammell>And the spans and the length of the spans that you must do can, I mean, we've got spans that

00:22:12.360 --> 00:22:15.360
<v Chris Gammell>can go up to six, 700 meters.

00:22:15.360 --> 00:22:16.360
<v Dave Jones>Oh, wow.

00:22:16.360 --> 00:22:17.360
<v Chris Gammell>Wow.

00:22:17.360 --> 00:22:18.360
<v Chris Gammell>Cheers.

00:22:18.360 --> 00:22:20.360
<v Chris Gammell>The stuff you see around in the, in the burbs, the 80 meter stuff, that's tiny.

00:22:20.360 --> 00:22:22.360
<v Chris Gammell>There's stuff that can go kilometer.

00:22:22.360 --> 00:22:23.360
<v Chris Gammell>Wow.

00:22:23.360 --> 00:22:24.360
<v Chris Gammell>Yeah.

00:22:24.360 --> 00:22:25.360
<v Dave Jones>Wow.

00:22:25.360 --> 00:22:27.360
<v Dave Jones>That's a heck of a, that's a heck of a droop on the wire.

00:22:27.360 --> 00:22:28.360
<v Dave Jones>Wow.

00:22:28.360 --> 00:22:31.360
<v Chris Gammell>You should try being the linesman that's got to crank the tension up on it.

00:22:31.360 --> 00:22:33.360
<v Dave Jones>I was going to say they would have tensioners, right?

00:22:33.360 --> 00:22:35.360
<v Chris Gammell>They've got to go up there periodically.

00:22:35.360 --> 00:22:36.360
<v Chris Gammell>Yeah.

00:22:36.360 --> 00:22:37.360
<v Chris Gammell>They're like, we call them lug alls.

00:22:37.360 --> 00:22:40.360
<v Chris Gammell>They're like a ratchet strap on your car, but obviously they're engineered.

00:22:40.360 --> 00:22:44.360
<v Chris Gammell>Um, you put a strap around the cross arm, you do what's called a come along, which it's

00:22:44.360 --> 00:22:47.360
<v Chris Gammell>kind of like, uh, you've been abseiling, haven't you?

00:22:47.360 --> 00:22:51.360
<v Chris Gammell>You, you know, you know, there's a device I think that lets you climb and only sort of

00:22:51.360 --> 00:22:52.360
<v Chris Gammell>goes one way.

00:22:52.360 --> 00:22:53.360
<v Chris Gammell>Yes.

00:22:53.360 --> 00:22:54.360
<v Chris Gammell>You can ascend up.

00:22:54.360 --> 00:22:55.360
<v Chris Gammell>Yeah.

00:22:55.360 --> 00:22:56.360
<v Chris Gammell>Yeah.

00:22:56.360 --> 00:22:57.360
<v Chris Gammell>Just one of them.

00:22:57.360 --> 00:22:58.360
<v Chris Gammell>You put it on the wire, you push it out.

00:22:58.360 --> 00:22:59.360
<v Chris Gammell>It goes outwards fine.

00:22:59.360 --> 00:23:03.360
<v Chris Gammell>You hook it up to your lug all and you start cranking it up and it pulls the tension in.

00:23:03.360 --> 00:23:04.360
<v Chris Gammell>And then you, um,

00:23:04.360 --> 00:23:06.360
<v Dave Jones>So do they have to adjust those differently during the seasons?

00:23:06.360 --> 00:23:08.360
<v Dave Jones>Cause I imagine summer's going to get hotter.

00:23:08.360 --> 00:23:11.360
<v Dave Jones>So it's going to expand and droop more maybe is that a thing?

00:23:11.360 --> 00:23:12.360
<v Chris Gammell>It does.

00:23:12.360 --> 00:23:13.360
<v Chris Gammell>They do sag.

00:23:13.360 --> 00:23:16.360
<v Chris Gammell>Um, they do sag based on temperature, but all the, all the calculations are done with

00:23:16.360 --> 00:23:18.360
<v Chris Gammell>the maximum sag and maximum current.

00:23:18.360 --> 00:23:19.360
<v Dave Jones>Got it.

00:23:19.360 --> 00:23:20.360
<v Dave Jones>Okay.

00:23:20.360 --> 00:23:21.360
<v Dave Jones>So you don't have to adjust it during the year.

00:23:21.360 --> 00:23:24.360
<v Dave Jones>You just have to periodically maintenance kind of.

00:23:24.360 --> 00:23:26.360
<v Chris Gammell>All the conductors, they're actually all quite different.

00:23:26.360 --> 00:23:31.360
<v Chris Gammell>Some of them are multi, they're all multi stranded, but some of them are an aluminium

00:23:31.360 --> 00:23:32.360
<v Chris Gammell>alloy.

00:23:32.360 --> 00:23:35.360
<v Chris Gammell>Some have a steel reinforcing core in the middle.

00:23:35.360 --> 00:23:37.360
<v Chris Gammell>You've got your, um, you've got your covered conductors.

00:23:37.360 --> 00:23:39.360
<v Chris Gammell>You've got your insulated conductors.

00:23:39.360 --> 00:23:44.360
<v Chris Gammell>You've got, um, bundled conductors and they're all quite different and they, they all have

00:23:44.360 --> 00:23:45.360
<v Chris Gammell>different roles.

00:23:45.360 --> 00:23:49.360
<v Chris Gammell>And if you start looking around the network, you'll, you'll start to identify some of the

00:23:49.360 --> 00:23:50.360
<v Chris Gammell>different ones.

00:23:50.360 --> 00:23:55.360
<v Chris Gammell>So, um, well just back on the transformers, I guess, cause that's, that's where I suppose

00:23:55.360 --> 00:23:59.360
<v Chris Gammell>some of your engineering crowd might be kind of interested is that each of the transformers,

00:23:59.360 --> 00:24:04.360
<v Chris Gammell>um, you know, they hooked to bars and the bars might have a breaker in between them to

00:24:04.360 --> 00:24:07.360
<v Chris Gammell>ties different sections of the bar together.

00:24:07.360 --> 00:24:13.360
<v Chris Gammell>And then each transformer itself will have a bar facing say the one 30, sorry, a breaker facing

00:24:13.360 --> 00:24:19.360
<v Chris Gammell>the one 32 and they'll have a breaker facing the 66 on the way out.

00:24:19.360 --> 00:24:25.360
<v Chris Gammell>Each of those breakers will have a VT, a voltage transformer, which takes a proportion of the voltage

00:24:25.360 --> 00:24:27.360
<v Chris Gammell>and takes it down to about a hundred volts.

00:24:27.360 --> 00:24:33.360
<v Chris Gammell>So we can measure the voltage on the bar and come in and out of the transformers proportion.

00:24:33.360 --> 00:24:41.360
<v Chris Gammell>They'll also have a CT, a current transformer, and that'll measure a proportion might be a 200 to 5 ratio

00:24:41.360 --> 00:24:43.360
<v Chris Gammell>or an 800 to 5 ratio.

00:24:43.360 --> 00:24:45.360
<v Chris Gammell>That'll measure a portion of the current.

00:24:45.360 --> 00:24:49.360
<v Dave Jones>How much loss is there in one of those current shunts?

00:24:49.360 --> 00:24:50.360
<v Chris Gammell>Not a lot.

00:24:50.360 --> 00:24:52.360
<v Chris Gammell>They're not current shunts per se.

00:24:52.360 --> 00:24:56.360
<v Chris Gammell>They're, um, they're, you know, when you get your, um, you know, your multimeter,

00:24:56.360 --> 00:24:58.360
<v Chris Gammell>your multimeter, that's got the, the clamp.

00:24:58.360 --> 00:24:59.360
<v Chris Gammell>They're a current transformer.

00:24:59.360 --> 00:25:00.360
<v Chris Gammell>Yes.

00:25:00.360 --> 00:25:03.360
<v Dave Jones>They're a current transformer, but they still got winding, winding loss in them.

00:25:03.360 --> 00:25:08.360
<v Chris Gammell>I guess you would call it one wire primary, but yeah, you just sample a portion of that.

00:25:08.360 --> 00:25:12.360
<v Chris Gammell>And that's how you sort of not only just look at the load going in and out of the transformer,

00:25:12.360 --> 00:25:14.360
<v Chris Gammell>but that's how all your protection works.

00:25:14.360 --> 00:25:20.360
<v Chris Gammell>So obviously you've got to protect on overcurrent and you've got to protect loss of phases.

00:25:20.360 --> 00:25:23.360
<v Chris Gammell>You've got to look at the voltage and monitor everything.

00:25:23.360 --> 00:25:27.360
<v Chris Gammell>And so, you know, all of those devices in the yard.

00:25:27.360 --> 00:25:31.360
<v Chris Gammell>And if you ever, you know, look in a yard, you might start to recognize some of them.

00:25:31.360 --> 00:25:37.360
<v Chris Gammell>They'll all, um, you know, sample the voltage and current, and that'll all come back to the SCADA control systems.

00:25:37.360 --> 00:25:38.360
<v Chris Gammell>And that's where things get crazy.

00:25:38.360 --> 00:25:45.360
<v Chris Gammell>This, you know, panels with relays in there that will measure everything and, um, you know, trip the breaker accordingly.

00:25:45.360 --> 00:25:55.360
<v Chris Gammell>But the arrangement of everything's kind of interesting because back in the old days, um, you know, your normal spinning meter that's inside your house.

00:25:55.360 --> 00:25:57.360
<v Chris Gammell>Well, it's, it's, um, it's technically a motor.

00:25:57.360 --> 00:25:58.360
<v Chris Gammell>It does measure power.

00:25:58.360 --> 00:26:00.360
<v Dave Jones>Yes. I've actually done a tear down video on those.

00:26:00.360 --> 00:26:01.360
<v Dave Jones>They're fascinating.

00:26:01.360 --> 00:26:02.360
<v Dave Jones>Absolutely fascinating.

00:26:02.360 --> 00:26:03.360
<v Dave Jones>Absolutely fascinating.

00:26:03.360 --> 00:26:09.360
<v Chris Gammell>Well, can you imagine getting one of those, but instead of hooking it up to a source, hooking it up to a CT.

00:26:09.360 --> 00:26:26.360
<v Chris Gammell>And so that, and imagine that it, imagine that it had a set of contacts on the disc and when the, and it's, let's say it's, um, you know, receiving normal current, it sort of slips and doesn't move, but above a certain amount of current, it starts to make the disc move.

00:26:26.360 --> 00:26:29.360
<v Dave Jones>Oh, and they'd physically have contacts on that.

00:26:29.360 --> 00:26:30.360
<v Dave Jones>Yeah.

00:26:30.360 --> 00:26:32.360
<v Dave Jones>Which then it detects that and then cuts it off.

00:26:32.360 --> 00:26:33.360
<v Chris Gammell>Yeah.

00:26:33.360 --> 00:26:38.360
<v Chris Gammell>And it works well because it follows the same inverse time constant.

00:26:38.360 --> 00:26:41.360
<v Chris Gammell>Really, the more current delivered to it, the faster it turns.

00:26:41.360 --> 00:26:42.360
<v Chris Gammell>Yes.

00:26:42.360 --> 00:26:49.360
<v Chris Gammell>And so it may only turn a quarter or half a turn, but you can literally put pegs in the disc that will trip a set of contacts.

00:26:49.360 --> 00:26:50.360
<v Dave Jones>Wow.

00:26:50.360 --> 00:26:54.360
<v Dave Jones>So it's a mechanical, it's effectively a, a mechanical solution.

00:26:54.360 --> 00:26:57.360
<v Chris Gammell>But we've gone past that now, but.

00:26:57.360 --> 00:26:58.360
<v Dave Jones>Oh, okay.

00:26:58.360 --> 00:26:59.360
<v Chris Gammell>Right.

00:26:59.360 --> 00:27:00.360
<v Chris Gammell>But they exist still.

00:27:00.360 --> 00:27:05.360
<v Chris Gammell>There's a few still out there with, but, but you know, the, the same sort of functionality has been replicated in software.

00:27:05.360 --> 00:27:08.360
<v Chris Gammell>Well, not in software, but in hardware, electronics, hardware.

00:27:08.360 --> 00:27:23.360
<v Chris Gammell>So, um, I can, will be programmed, but you know, breakers, they're interesting to be because if you imagine an 11 KV distribution breaker, feeding power outside onto the poles and wires has a fault or over current.

00:27:23.360 --> 00:27:26.360
<v Chris Gammell>It may, it will trip the breaker.

00:27:26.360 --> 00:27:31.360
<v Chris Gammell>And the break has a set of contacts that will tell you if the break is open or closed.

00:27:31.360 --> 00:27:42.360
<v Chris Gammell>If it doesn't trip or the moment it goes to trip, the upstream breaker timer also starts because if that break, it doesn't trip that transformer will be in trouble.

00:27:42.360 --> 00:27:43.360
<v Chris Gammell>Oh, got it.

00:27:43.360 --> 00:27:47.360
<v Chris Gammell>So the next point of call is to turn the transformer off and trip it.

00:27:47.360 --> 00:27:48.360
<v Dave Jones>Oh, okay.

00:27:48.360 --> 00:27:52.360
<v Dave Jones>So it talks upstream and goes, Hey, I've got a problem.

00:27:52.360 --> 00:27:54.360
<v Dave Jones>Be on standby, be on ready timer for.

00:27:54.360 --> 00:27:55.360
<v Dave Jones>Yeah.

00:27:55.360 --> 00:27:56.360
<v Dave Jones>So both timers will start.

00:27:56.360 --> 00:28:04.360
<v Chris Gammell>And if the, if the breaker doesn't open and those contacts don't show that the breaker opened, then the upstream breaker will trip.

00:28:04.360 --> 00:28:06.360
<v Dave Jones>Will trip just in case that yeah.

00:28:06.360 --> 00:28:07.360
<v Chris Gammell>It will absolutely trip.

00:28:07.360 --> 00:28:10.360
<v Dave Jones>So that's, that's a fault prevention on top of a fault.

00:28:10.360 --> 00:28:11.360
<v Chris Gammell>Yeah.

00:28:11.360 --> 00:28:18.360
<v Chris Gammell>And that's why we probably wouldn't have that runaway problem because our protection is really good like that.

00:28:18.360 --> 00:28:24.360
<v Chris Gammell>Most of it's duplicated with standby relays as well, especially in the transmission zone subs.

00:28:24.360 --> 00:28:26.360
<v Chris Gammell>They're also battery backed up as well.

00:28:27.360 --> 00:28:28.360
<v Dave Jones>Right.

00:28:28.360 --> 00:28:29.360
<v Dave Jones>Interesting.

00:28:29.360 --> 00:28:31.360
<v Chris Gammell>And the control room knows what's going on as well.

00:28:31.360 --> 00:28:32.360
<v Dave Jones>Right.

00:28:32.360 --> 00:28:35.360
<v Dave Jones>What happens if ironically power fails to the control room?

00:28:35.360 --> 00:28:38.360
<v Dave Jones>You have a battery backup, DC battery.

00:28:38.360 --> 00:28:39.360
<v Dave Jones>Right.

00:28:39.360 --> 00:28:40.360
<v Dave Jones>So there is a DC battery in the substation.

00:28:40.360 --> 00:28:42.360
<v Dave Jones>Yeah, they do have AGM batteries there.

00:28:42.360 --> 00:28:43.360
<v Dave Jones>Right.

00:28:43.360 --> 00:28:44.360
<v Dave Jones>Yep.

00:28:44.360 --> 00:28:45.360
<v Dave Jones>Okay.

00:28:45.360 --> 00:28:46.360
<v Dave Jones>All of them.

00:28:46.360 --> 00:28:47.360
<v Dave Jones>Yep.

00:28:47.360 --> 00:28:48.360
<v Dave Jones>Right.

00:28:48.360 --> 00:28:52.360
<v Dave Jones>I didn't think about that, but yeah, ironically, what if the power to the power station fails?

00:28:52.360 --> 00:28:53.360
<v Chris Gammell>Yeah.

00:28:53.360 --> 00:28:56.360
<v Chris Gammell>The testing and commission and building of those is really fun job.

00:28:56.360 --> 00:29:00.360
<v Chris Gammell>Like it's a really cool, interesting job because I don't know if you've seen them.

00:29:00.360 --> 00:29:01.360
<v Chris Gammell>They make these things called dobles.

00:29:01.360 --> 00:29:10.360
<v Chris Gammell>They're like a big power supply that's fully programmable and can put out, you know, voltages up to a thousand volts at whatever frequency and current you want.

00:29:10.360 --> 00:29:17.360
<v Chris Gammell>And then they have sort of logic inputs that can, you know, that you can see when they've triggered.

00:29:17.360 --> 00:29:19.360
<v Chris Gammell>So you might hook it up to a breaker.

00:29:19.360 --> 00:29:27.360
<v Chris Gammell>You might wrap, wrap the output around the CT a few times to double up or quadruple up the current, inject some current and see if the breaker trips.

00:29:27.360 --> 00:29:36.360
<v Chris Gammell>When the breaker trips, when the breaker trips and those contacts open, the double will tell you the time in milliseconds, you know, and then you can check all your tripping curves.

00:29:36.360 --> 00:29:39.360
<v Chris Gammell>It's a lot of, a lot of fun to build all that, that gear.

00:29:39.360 --> 00:29:45.360
<v Chris Gammell>There's, you know, like I said, CTs, VTs and the breakers and there's even standby equipment.

00:29:45.360 --> 00:29:47.360
<v Chris Gammell>The breaker might be split in half.

00:29:47.360 --> 00:29:58.360
<v Chris Gammell>And so if a transformer fails and locks out, the bus tie breaker might close and bring in the standby transformer or put all the load onto one of the other transformers as well.

00:29:58.360 --> 00:30:02.360
<v Dave Jones>Okay. So you will, every substation will have a standby transformer.

00:30:02.360 --> 00:30:12.360
<v Chris Gammell>Will it not every substation, but a lot of, a lot of electrical equipment can handle overload a lot higher than its normal load.

00:30:12.360 --> 00:30:17.360
<v Chris Gammell>So maybe 150, 200% of its normal rate of capacity.

00:30:17.360 --> 00:30:24.360
<v Dave Jones>Okay. That's quite a lot, but, but you wouldn't want to do that for like a week or something you want to, you could do that for a day or half a day or something.

00:30:24.360 --> 00:30:27.360
<v Chris Gammell>You might pull a transformer out of service to work on it.

00:30:27.360 --> 00:30:28.360
<v Chris Gammell>Oh, okay. Yeah, of course.

00:30:28.360 --> 00:30:31.360
<v Chris Gammell>So you might isolate and pull it out of service. Yeah.

00:30:31.360 --> 00:30:38.360
<v Chris Gammell>And then of course you've lost that, you've lost that backup capacity, but it's usually, you know, been planned around.

00:30:38.360 --> 00:30:40.360
<v Chris Gammell>They'll, they'll have a, they'll have a plan.

00:30:40.360 --> 00:30:46.360
<v Dave Jones>Right. So what are the usual failure modes that cause a transformer, like a substation trip?

00:30:46.360 --> 00:30:48.360
<v Dave Jones>What's, what's the usual fault down the line?

00:30:48.360 --> 00:30:51.360
<v Chris Gammell>They don't really, the transformers don't really fail, but mostly.

00:30:51.360 --> 00:30:55.360
<v Dave Jones>Mostly. No, no, I'm talking about what, what causes the breaker to trees.

00:30:55.360 --> 00:30:57.360
<v Chris Gammell>Trees, trees on power lines.

00:30:57.360 --> 00:30:59.360
<v Dave Jones>So it's, so it's shorted power lines, right?

00:30:59.360 --> 00:31:03.360
<v Dave Jones>So it's shorted and open power lines.

00:31:03.360 --> 00:31:12.360
<v Dave Jones>Because if people aren't aware, they, most transmission lines in that you see like power poles and stuff, there are three phases.

00:31:12.360 --> 00:31:14.360
<v Dave Jones>That's why they have the three wires on the top.

00:31:14.360 --> 00:31:22.360
<v Chris Gammell>Yeah. So the high voltage networks, three phase and it's three wires and they come into the transformer and they terminate in a delta configuration.

00:31:22.360 --> 00:31:24.360
<v Chris Gammell>So they just, it's like a triangle.

00:31:24.360 --> 00:31:26.360
<v Chris Gammell>Imagine the wires attached to each point of the triangle.

00:31:26.360 --> 00:31:30.360
<v Chris Gammell>The sides of the triangle are one of the coils in the transformer.

00:31:30.360 --> 00:31:36.360
<v Chris Gammell>And then on the secondary side, you'll have four wires because it's in star.

00:31:36.360 --> 00:31:38.360
<v Dave Jones>Yes. Oh, star and delta transforms.

00:31:38.360 --> 00:31:45.360
<v Dave Jones>I kind of remember those from, I don't, I don't think I could do it today, but like straight off my head, but you know.

00:31:45.360 --> 00:31:51.360
<v Chris Gammell>One of the questions I like to ask the, the apprentices is, you know, what are three phases add up to?

00:31:51.360 --> 00:31:55.360
<v Chris Gammell>Now you hear a lot of things, but do you want to take a guess, though?

00:31:55.360 --> 00:31:57.360
<v Chris Gammell>What three phases add up to?

00:31:57.360 --> 00:31:59.360
<v Dave Jones>Three phases adds up to, I don't know.

00:31:59.360 --> 00:32:01.360
<v Dave Jones>Three phases.

00:32:01.360 --> 00:32:05.360
<v Dave Jones>No, it's, you're obviously a trick question and I'm just going to embarrass myself.

00:32:05.360 --> 00:32:06.360
<v Dave Jones>Yeah, zero. Zero.

00:32:06.360 --> 00:32:07.360
<v Chris Gammell>Zero, right.

00:32:07.360 --> 00:32:11.360
<v Chris Gammell>Because that's where that neutral point, the center of that star, that's where it's derived.

00:32:11.360 --> 00:32:12.360
<v Chris Gammell>Yes, okay.

00:32:12.360 --> 00:32:12.360
<v Speaker ?>

00:32:12.360 --> 00:32:14.360
<v Chris Gammell>And that's at ground potential.

00:32:14.360 --> 00:32:16.360
<v Chris Gammell>Now we actually get our neutral.

00:32:16.360 --> 00:32:18.360
<v Dave Jones>Now, yeah, it's all flooding back.

00:32:18.360 --> 00:32:19.360
<v Dave Jones>I totally remember.

00:32:19.360 --> 00:32:21.360
<v Dave Jones>Yeah, we had that question in an exam one time.

00:32:21.360 --> 00:32:22.360
<v Chris Gammell>Yeah.

00:32:22.360 --> 00:32:23.360
<v Dave Jones>I totally remember that.

00:32:23.360 --> 00:32:24.360
<v Dave Jones>Yeah.

00:32:24.360 --> 00:32:28.360
<v Chris Gammell>Oh, the, the, the mathematics around phaser calculations.

00:32:28.360 --> 00:32:29.360
<v Chris Gammell>It's not fun to do.

00:32:29.360 --> 00:32:30.360
<v Chris Gammell>No.

00:32:30.360 --> 00:32:32.360
<v Chris Gammell>Three phases are out of phase by about 120 degrees.

00:32:32.360 --> 00:32:37.360
<v Dave Jones>I can kind of remember enjoying it at the time, but I can bet, you know, it was like, meh, how am I going to use this?

00:32:37.360 --> 00:32:39.360
<v Chris Gammell>Well, our power engineers do.

00:32:39.360 --> 00:32:44.360
<v Chris Gammell>They, they look at bolted faults, what we call a bolted fault, which is like basically a

00:32:44.360 --> 00:32:46.360
<v Chris Gammell>basically as if the wires were bolted together, two phases.

00:32:46.360 --> 00:32:49.360
<v Chris Gammell>What's going to be the negative sequence current for that?

00:32:49.360 --> 00:32:52.360
<v Chris Gammell>You know, which, which way is the voltage going to go?

00:32:52.360 --> 00:32:54.360
<v Chris Gammell>What, how much current's going to flow?

00:32:54.360 --> 00:32:58.360
<v Chris Gammell>Because the amount of current flows depending on, depends on the impedance of the transformer.

00:32:58.360 --> 00:33:01.360
<v Chris Gammell>They have an impedance of around seven and a half percent.

00:33:01.360 --> 00:33:13.360
<v Chris Gammell>So, um, that means, you know, a hundred divided by 7.5, whatever that is, um, is, you know, if they're normal currents, a hundred amps, it'll be, you know, 20 times a hundred amps.

00:33:13.360 --> 00:33:15.360
<v Chris Gammell>It'll be their fault current, you know?

00:33:15.360 --> 00:33:16.360
<v Dave Jones>So, right.

00:33:16.360 --> 00:33:18.360
<v Dave Jones>Cause I can imagine that's tricky.

00:33:18.360 --> 00:33:25.360
<v Dave Jones>Imagine if, you know, your longest transmission line, you can imagine as the short right at the end of the transmission line, you've got all the other loads on there.

00:33:25.360 --> 00:33:27.360
<v Dave Jones>Would you still be able to, how do you pick that up?

00:33:27.360 --> 00:33:29.360
<v Chris Gammell>We have two types of protection.

00:33:29.360 --> 00:33:32.360
<v Chris Gammell>We have, well, there's lots of protection schemes.

00:33:32.360 --> 00:33:33.360
<v Chris Gammell>There really are.

00:33:33.360 --> 00:33:38.360
<v Chris Gammell>And they're individually tailored and designed for the kinds of equipment and that are present there.

00:33:38.360 --> 00:33:45.360
<v Chris Gammell>And the back, like the backup cycle said, if there's a second transformer or not, a bus tie breaker mightn't be there, you know, all those sorts of things.

00:33:45.360 --> 00:33:52.360
<v Chris Gammell>But yeah, we, we use an, an earth fault protection and that's like, um, you know, a certain amount.

00:33:52.360 --> 00:33:56.360
<v Chris Gammell>So we, of course we've got all the usuals under voltage, over voltage, over current protection.

00:33:56.360 --> 00:34:04.360
<v Chris Gammell>They're all there, but for a conductor, um, you know, touching the ground or earthing or something like that, a fault like that.

00:34:04.360 --> 00:34:06.360
<v Chris Gammell>We use, um, two types.

00:34:06.360 --> 00:34:12.360
<v Chris Gammell>We use a sensitive earth fault protection and that's a lower current, but for a longer period.

00:34:12.360 --> 00:34:17.360
<v Chris Gammell>And then we've got our earth protection, which might be, you know, five amps or five seconds would trip.

00:34:17.360 --> 00:34:25.360
<v Chris Gammell>But a sensitive earth fault might be as low as one amp, but it might need about 30 or 40 seconds to be, you know, seen for that length of time.

00:34:25.360 --> 00:34:27.360
<v Chris Gammell>And it says, right, there's something not right here.

00:34:27.360 --> 00:34:30.360
<v Dave Jones>Because you don't, it's a trade off, wouldn't it?

00:34:30.360 --> 00:34:39.360
<v Dave Jones>It'd be a trade off between actually protecting your transformer or another infrastructure and allowing, like, nuisance tripping.

00:34:39.360 --> 00:34:49.360
<v Dave Jones>Like I've had, like, I came back from holidays one time and all my fridges were filled with moldy growth because we, our power fight, the earth leakage circuit breaker tripped.

00:34:49.360 --> 00:34:50.360
<v Dave Jones>Yeah.

00:34:50.360 --> 00:34:51.360
<v Dave Jones>For tripped.

00:34:51.360 --> 00:34:52.360
<v Dave Jones>And then it just, yeah.

00:34:52.360 --> 00:34:56.360
<v Chris Gammell>I think that's why you got yourself that little, um, that little power bank.

00:34:56.360 --> 00:34:57.360
<v Dave Jones>That, that little power bank.

00:34:57.360 --> 00:34:58.360
<v Dave Jones>Yes.

00:34:58.360 --> 00:34:59.360
<v Dave Jones>Yeah.

00:34:59.360 --> 00:35:00.360
<v Dave Jones>The battery bank thing.

00:35:00.360 --> 00:35:01.360
<v Chris Gammell>Yeah.

00:35:01.360 --> 00:35:02.360
<v Dave Jones>It's like, yeah.

00:35:02.360 --> 00:35:03.360
<v Dave Jones>Bloody annoying.

00:35:03.360 --> 00:35:04.360
<v Dave Jones>Yeah.

00:35:04.360 --> 00:35:05.360
<v Dave Jones>So it'd be a trade off, right?

00:35:05.360 --> 00:35:12.360
<v Dave Jones>Between sort of nuisance things, because your job is ultimately to deliver power to a massive load of thousands of customers, right?

00:35:12.360 --> 00:35:15.360
<v Dave Jones>Tens of thousands of customers while protecting your equipment.

00:35:15.360 --> 00:35:16.360
<v Dave Jones>Oh, it's a million.

00:35:16.360 --> 00:35:17.360
<v Dave Jones>Million, right?

00:35:17.360 --> 00:35:18.360
<v Chris Gammell>Yeah.

00:35:18.360 --> 00:35:19.360
<v Chris Gammell>About a million plus customers.

00:35:19.360 --> 00:35:20.360
<v Dave Jones>Oh, wow.

00:35:20.360 --> 00:35:25.360
<v Chris Gammell>About 32,000 or so of those are on, uh, what we call a life support customer as well.

00:35:25.360 --> 00:35:30.360
<v Chris Gammell>Someone that needs electricity to keep their medicines cold, to help with their oxygen concentrators.

00:35:30.360 --> 00:35:36.360
<v Dave Jones>Hospitals would be on a totally different, would, you know, how would you wire up a hospital different, would you give them a backup transformer and a priority?

00:35:36.360 --> 00:35:38.360
<v Dave Jones>They have their own feeder usually.

00:35:38.360 --> 00:35:43.360
<v Chris Gammell>They don't usually, that feeder's marked in the zone sub so that we know that it is a hospital feeder.

00:35:43.360 --> 00:35:46.360
<v Chris Gammell>They also have a lot of their own generators as well.

00:35:46.360 --> 00:35:47.360
<v Dave Jones>Of course.

00:35:47.360 --> 00:35:48.360
<v Chris Gammell>Yeah.

00:35:48.360 --> 00:35:52.360
<v Chris Gammell>There's a lot, you know, 430 odd thousand power poles around.

00:35:52.360 --> 00:35:58.360
<v Dave Jones>Oh, what is the difference between, yeah, I mentioned this at the start of the thing, underground and, uh, poles.

00:35:58.360 --> 00:36:02.360
<v Dave Jones>Cause my house and suburb is all underground power.

00:36:02.360 --> 00:36:08.360
<v Dave Jones>And I like, that's a good thing for, as far as the consumer's concerned, cause you don't see these pesky power poles.

00:36:08.360 --> 00:36:14.360
<v Dave Jones>There's less potential interruptions from trees and lightning and cars hitting them and you know, all sorts of things.

00:36:14.360 --> 00:36:15.360
<v Dave Jones>So what is the difference?

00:36:15.360 --> 00:36:19.360
<v Dave Jones>And do you, do you guys have a, uh, preference for underground?

00:36:19.360 --> 00:36:21.360
<v Dave Jones>Is it more difficult to work on?

00:36:21.360 --> 00:36:22.360
<v Chris Gammell>What kind is it?

00:36:22.360 --> 00:36:28.360
<v Chris Gammell>From what I understand, all new developments need to be, um, underground.

00:36:28.360 --> 00:36:33.360
<v Chris Gammell>They need to demonstrate a reason why they can't be or shouldn't be.

00:36:33.360 --> 00:36:38.360
<v Chris Gammell>They might be a rural subdivision, but in general, they, they, they like them to be underground.

00:36:38.360 --> 00:36:45.360
<v Chris Gammell>I guess in a rural area, the aerial conductors, they're very easy to put back up in the air.

00:36:45.360 --> 00:36:47.360
<v Chris Gammell>They're very fast to restore supply.

00:36:47.360 --> 00:36:56.360
<v Chris Gammell>Um, there's some associated, um, let's see, not difficulties, but when you switch with underground, it's inside cubicles.

00:36:56.360 --> 00:37:02.360
<v Chris Gammell>Um, it's a little different the way we do underground switching.

00:37:02.360 --> 00:37:04.360
<v Chris Gammell>You can't trace the conductors as easily.

00:37:04.360 --> 00:37:14.360
<v Chris Gammell>So like to, to be a switcher on the network for underground is a slightly higher qualification in general, but, but underground, you're right.

00:37:14.360 --> 00:37:21.360
<v Chris Gammell>It's when there's a fault, it might be a little harder though, because you, you might have to dig up everyone's, you know, the front, front driveways or whatever.

00:37:21.360 --> 00:37:22.360
<v Dave Jones>Yeah. Right.

00:37:23.360 --> 00:37:27.360
<v Dave Jones>But, um, but, um, but faults like, uh, water ingress in the, in the wires underground.

00:37:27.360 --> 00:37:29.360
<v Dave Jones>Is that a problem or?

00:37:29.360 --> 00:37:30.360
<v Chris Gammell>Yeah, it doesn't really, it doesn't.

00:37:30.360 --> 00:37:31.360
<v Chris Gammell>Okay.

00:37:31.360 --> 00:37:32.360
<v Chris Gammell>Does it right?

00:37:32.360 --> 00:37:33.360
<v Chris Gammell>No, not at all.

00:37:33.360 --> 00:37:38.360
<v Chris Gammell>Um, they, they also, believe it or not, the conductors actually are a little cooler in the ground.

00:37:38.360 --> 00:37:42.360
<v Chris Gammell>Um, you can overrate a conductor and it's buried.

00:37:42.360 --> 00:37:43.360
<v Chris Gammell>Right.

00:37:43.360 --> 00:37:44.360
<v Dave Jones>Okay.

00:37:44.360 --> 00:37:48.360
<v Dave Jones>So they, you could potentially get away with a lower rating cable or more, more power for a given.

00:37:48.360 --> 00:37:51.360
<v Chris Gammell>Just that they, they're just a little bit more secure down there as well.

00:37:51.360 --> 00:37:54.360
<v Chris Gammell>And they have a benefit of the cooler, cooler environment as well.

00:37:54.360 --> 00:37:56.360
<v Chris Gammell>Um, and then.

00:37:56.360 --> 00:37:57.360
<v Chris Gammell>Um, and then.

00:37:57.360 --> 00:38:02.360
<v Dave Jones>Is there any extra loss in terms of like power factor and capacitance and all that sort of jazz?

00:38:02.360 --> 00:38:03.360
<v Dave Jones>Is that.

00:38:03.360 --> 00:38:04.360
<v Dave Jones>Mm.

00:38:04.360 --> 00:38:07.360
<v Dave Jones>Cause I think it makes a difference on really high voltage DC.

00:38:07.360 --> 00:38:08.360
<v Dave Jones>Yeah.

00:38:08.360 --> 00:38:08.360
<v Speaker ?>

00:38:08.360 --> 00:38:09.360
<v Dave Jones>Yeah.

00:38:09.360 --> 00:38:10.360
<v Dave Jones>You do.

00:38:10.360 --> 00:38:14.360
<v Chris Gammell>I mean, you, you get, um, you do get a little, like when you, it's funny when you're testing

00:38:14.360 --> 00:38:19.360
<v Chris Gammell>cables, if there's, um, you got three phases and only one's energized, you will see a voltage

00:38:19.360 --> 00:38:20.360
<v Chris Gammell>on the other two phases.

00:38:20.360 --> 00:38:24.360
<v Chris Gammell>So you do get that induction, but, um, not that I know.

00:38:24.360 --> 00:38:27.360
<v Chris Gammell>A lot of them are, um, still copper actually, a lot of the underground stuff.

00:38:27.360 --> 00:38:28.360
<v Chris Gammell>So that's.

00:38:28.360 --> 00:38:29.360
<v Dave Jones>Oh, right.

00:38:29.360 --> 00:38:30.360
<v Dave Jones>Oh, cause weight's not an issue anymore.

00:38:30.360 --> 00:38:31.360
<v Dave Jones>So I guess it's.

00:38:31.360 --> 00:38:34.360
<v Chris Gammell>I wonder, would it be cheaper copper or.

00:38:35.360 --> 00:38:36.360
<v Dave Jones>Aluminium.

00:38:36.360 --> 00:38:38.360
<v Chris Gammell>Aluminium is a lot cheaper from what I understand.

00:38:38.360 --> 00:38:39.360
<v Chris Gammell>It's just cheaper.

00:38:39.360 --> 00:38:40.360
<v Dave Jones>Okay.

00:38:40.360 --> 00:38:41.360
<v Dave Jones>Yeah.

00:38:41.360 --> 00:38:42.360
<v Dave Jones>Yeah.

00:38:42.360 --> 00:38:43.360
<v Dave Jones>Cause obviously cost is a big part too.

00:38:43.360 --> 00:38:44.360
<v Dave Jones>Yeah.

00:38:44.360 --> 00:38:45.360
<v Chris Gammell>Yeah.

00:38:45.360 --> 00:38:48.360
<v Chris Gammell>Cost in electricity has become a bit of a thing lately.

00:38:48.360 --> 00:38:51.360
<v Chris Gammell>And as you know, like the renewables are just going crazy at the moment.

00:38:51.360 --> 00:38:52.360
<v Chris Gammell>Oh yeah.

00:38:52.360 --> 00:38:53.360
<v Chris Gammell>Yeah.

00:38:53.360 --> 00:38:55.360
<v Chris Gammell>A lot of things happening in that space.

00:38:55.360 --> 00:38:56.360
<v Dave Jones>Right.

00:38:56.360 --> 00:38:58.360
<v Dave Jones>You got any personal thoughts on that?

00:38:58.360 --> 00:39:01.360
<v Dave Jones>Whether or not that's a good thing, bad thing, troublesome.

00:39:01.360 --> 00:39:02.360
<v Chris Gammell>I think it's good.

00:39:02.360 --> 00:39:06.360
<v Chris Gammell>I, I, I don't know about you, but I've got, I've had solar for a few years now.

00:39:06.360 --> 00:39:07.360
<v Chris Gammell>Yeah.

00:39:07.360 --> 00:39:08.360
<v Dave Jones>Same here.

00:39:08.360 --> 00:39:09.360
<v Dave Jones>I've, I've had it forever.

00:39:09.360 --> 00:39:10.360
<v Chris Gammell>Yeah.

00:39:10.360 --> 00:39:11.360
<v Chris Gammell>Um, I'd like an electric vehicle if I could.

00:39:11.360 --> 00:39:12.360
<v Dave Jones>Yep.

00:39:12.360 --> 00:39:13.360
<v Dave Jones>Got one.

00:39:13.360 --> 00:39:14.360
<v Chris Gammell>They're great.

00:39:14.360 --> 00:39:15.360
<v Dave Jones>But they're not for everyone.

00:39:15.360 --> 00:39:16.360
<v Dave Jones>Of course, you know.

00:39:16.360 --> 00:39:17.360
<v Chris Gammell>No.

00:39:17.360 --> 00:39:21.360
<v Chris Gammell>Community batteries are a sort of virtual power plants.

00:39:21.360 --> 00:39:26.360
<v Chris Gammell>I like the idea of say, like at the moment, you know, you sell your power to the grid.

00:39:26.360 --> 00:39:29.360
<v Chris Gammell>It'd be kind of nice if they were to bank that power somehow.

00:39:29.360 --> 00:39:32.360
<v Chris Gammell>And, um, you know, give you the chance to buy it back in a battery.

00:39:32.360 --> 00:39:33.360
<v Dave Jones>Yeah.

00:39:33.360 --> 00:39:36.360
<v Dave Jones>Like, I know that I'm generating excess solar into the grid.

00:39:36.360 --> 00:39:38.360
<v Dave Jones>I know that my neighbors are using it.

00:39:38.360 --> 00:39:44.360
<v Dave Jones>Why can't like, we have like a little neighborhood monitoring thing that like, oh, I know it's

00:39:44.360 --> 00:39:45.360
<v Dave Jones>being used by my neighbor.

00:39:45.360 --> 00:39:47.360
<v Dave Jones>Oh, I can just charge my neighbor.

00:39:47.360 --> 00:39:50.360
<v Dave Jones>And like, you can buy, literally buy it off your neighbor.

00:39:50.360 --> 00:39:51.360
<v Chris Gammell>Yeah.

00:39:51.360 --> 00:39:53.360
<v Chris Gammell>They have community batteries around the place too.

00:39:53.360 --> 00:39:57.360
<v Chris Gammell>And they, they actually, um, and virtual power plants, I think they call them, but they,

00:39:57.360 --> 00:40:00.360
<v Chris Gammell>they also increase resilience a lot too.

00:40:00.360 --> 00:40:04.360
<v Chris Gammell>Um, we've got some places down the coast that were badly affected by bushfires and they can

00:40:04.360 --> 00:40:06.360
<v Chris Gammell>get isolated for quite a while.

00:40:06.360 --> 00:40:10.360
<v Chris Gammell>Because I think the thing about Australia, it's such a large country.

00:40:10.360 --> 00:40:13.360
<v Chris Gammell>We've got these transmission lines running everywhere.

00:40:13.360 --> 00:40:19.360
<v Chris Gammell>Um, you know, and the power does come from a long way from where it's consumed.

00:40:19.360 --> 00:40:24.360
<v Chris Gammell>And so, you know, it's got to pass through, you know, rural areas and they're often subject

00:40:24.360 --> 00:40:30.360
<v Chris Gammell>to a lot of, you know, disruption from storm and floods and fires and stuff.

00:40:30.360 --> 00:40:31.360
<v Chris Gammell>Yeah.

00:40:31.360 --> 00:40:32.360
<v Chris Gammell>And it can impact the communities a lot.

00:40:32.360 --> 00:40:35.360
<v Chris Gammell>So having a little local storage is probably a good idea.

00:40:35.360 --> 00:40:39.360
<v Chris Gammell>I mean, I, I like the idea of, um, a bit of renewable scattered around.

00:40:39.360 --> 00:40:40.360
<v Chris Gammell>Isn't that what we're working for anyway?

00:40:40.360 --> 00:40:43.360
<v Chris Gammell>I mean, you know, working towards a better sort of.

00:40:43.360 --> 00:40:44.360
<v Dave Jones>Oh yeah, no, totally.

00:40:44.360 --> 00:40:45.360
<v Dave Jones>We want to, you know, to get it.

00:40:45.360 --> 00:40:46.360
<v Dave Jones>Yeah.

00:40:46.360 --> 00:40:51.360
<v Dave Jones>I would like, I mean, what I think Australia has the highest solar uptake in the world,

00:40:51.360 --> 00:40:52.360
<v Dave Jones>right?

00:40:52.360 --> 00:40:55.360
<v Dave Jones>Like 35, even 40% of homes have solar now.

00:40:55.360 --> 00:40:56.360
<v Chris Gammell>Well, it's massive.

00:40:56.360 --> 00:40:57.360
<v Chris Gammell>Yeah.

00:40:57.360 --> 00:41:02.360
<v Chris Gammell>It's a, well, we've got, supposedly we've got over 200,000 customers that have some sort

00:41:02.360 --> 00:41:05.360
<v Chris Gammell>of renewal, renewable energy system at home.

00:41:05.360 --> 00:41:06.360
<v Chris Gammell>That is just in.

00:41:06.360 --> 00:41:07.360
<v Dave Jones>Out of a million.

00:41:07.360 --> 00:41:08.360
<v Chris Gammell>Our state.

00:41:08.360 --> 00:41:10.360
<v Chris Gammell>Just in my, the company I work for.

00:41:10.360 --> 00:41:11.360
<v Chris Gammell>Oh, just the company.

00:41:11.360 --> 00:41:12.360
<v Chris Gammell>So yeah.

00:41:12.360 --> 00:41:13.360
<v Chris Gammell>Yeah.

00:41:13.360 --> 00:41:18.360
<v Chris Gammell>So we're, we're just sort of Western Sydney, sort of, we go sort of north of Kandos up there

00:41:18.360 --> 00:41:24.360
<v Chris Gammell>to Bylong and Katoomba and South Dalladala and into Parramatta and big area.

00:41:24.360 --> 00:41:27.360
<v Dave Jones>That's just, yeah, that's a huge number of people.

00:41:27.360 --> 00:41:34.360
<v Dave Jones>Now, if you're a linesman, you're working on a line, how much of a fear do you have of,

00:41:34.360 --> 00:41:37.360
<v Dave Jones>oh, somebody's installed a non-compliant solar thing?

00:41:37.360 --> 00:41:38.360
<v Dave Jones>You've, you've gone in there.

00:41:38.360 --> 00:41:41.360
<v Dave Jones>You've actually locked out the grid with your padlocks and everything.

00:41:41.360 --> 00:41:42.360
<v Dave Jones>Yeah.

00:41:42.360 --> 00:41:43.360
<v Dave Jones>We actually don't.

00:41:43.360 --> 00:41:44.360
<v Dave Jones>Some bastards.

00:41:44.360 --> 00:41:48.360
<v Chris Gammell>I tell you, Dave, if I was fearful, I'd be worried we're doing something wrong.

00:41:48.360 --> 00:41:54.360
<v Chris Gammell>We, we are very good at protecting ourselves and our, and the work, you know, my mates.

00:41:54.360 --> 00:41:58.360
<v Chris Gammell>Um, we always, um, isolate.

00:41:58.360 --> 00:41:59.360
<v Chris Gammell>We test the isolation.

00:41:59.360 --> 00:42:01.360
<v Chris Gammell>We lock it and test it.

00:42:01.360 --> 00:42:02.360
<v Chris Gammell>We danger tag it.

00:42:02.360 --> 00:42:04.360
<v Chris Gammell>And then we bond it.

00:42:04.360 --> 00:42:06.360
<v Chris Gammell>So we generally with the high voltage network.

00:42:06.360 --> 00:42:07.360
<v Chris Gammell>Okay.

00:42:07.360 --> 00:42:08.360
<v Dave Jones>So you would strap it.

00:42:08.360 --> 00:42:09.360
<v Dave Jones>You would have it.

00:42:09.360 --> 00:42:10.360
<v Dave Jones>Yeah.

00:42:10.360 --> 00:42:16.360
<v Chris Gammell>We run special, special, highly rated, um, uh, bonds between the, between the phases and then down to earth.

00:42:16.360 --> 00:42:26.360
<v Chris Gammell>And when it comes to, you know, our, the solar installations, we don't necessarily, um, go through and isolate them all from what I remember.

00:42:26.360 --> 00:42:28.360
<v Chris Gammell>But like I said, I just have to preface this.

00:42:28.360 --> 00:42:34.360
<v Chris Gammell>I have been in the, out of the field for a couple of years now, just a couple, but I keep my mind everything.

00:42:34.360 --> 00:42:38.360
<v Chris Gammell>And yeah, they, they use bonds on the LV network now as well.

00:42:38.360 --> 00:42:46.360
<v Chris Gammell>And they, you know, just because all, all our, um, the, the, what islandings, that what they call it when they.

00:42:46.360 --> 00:42:46.360
<v Speaker ?>

00:42:46.360 --> 00:42:47.360
<v Chris Gammell>Yes.

00:42:47.360 --> 00:42:56.360
<v Dave Jones>Every, every solar inverter in this country that's sold in this country must have auto islanding, which means that if the grid fails, you can't, it, it will shut down.

00:42:56.360 --> 00:42:58.360
<v Dave Jones>It'll shut off its output and it won't export.

00:42:58.360 --> 00:42:59.360
<v Dave Jones>If it doesn't see that.

00:42:59.360 --> 00:43:00.360
<v Chris Gammell>Yeah.

00:43:00.360 --> 00:43:04.360
<v Dave Jones>If it, if it doesn't see the grid, it won't, uh, generate any power.

00:43:04.360 --> 00:43:08.360
<v Dave Jones>That's why if power to my home fails, I don't care how big my solar system is.

00:43:08.360 --> 00:43:09.360
<v Dave Jones>It's just going to shut off.

00:43:09.360 --> 00:43:10.360
<v Dave Jones>You can't use it.

00:43:10.360 --> 00:43:11.360
<v Dave Jones>Right.

00:43:11.360 --> 00:43:12.360
<v Dave Jones>You can't use it.

00:43:12.360 --> 00:43:13.360
<v Dave Jones>So you've got to have like a local battery.

00:43:13.360 --> 00:43:18.360
<v Dave Jones>You've got to have an AC battery solution, or you've got to have a local islanding, um, battery solution at your home.

00:43:18.360 --> 00:43:19.360
<v Dave Jones>So yeah, it's got to shut off.

00:43:19.360 --> 00:43:20.360
<v Dave Jones>Yeah.

00:43:20.360 --> 00:43:26.360
<v Chris Gammell>So we, we don't worry too much when we're working on the network because it really is safe and it's really isolated.

00:43:26.360 --> 00:43:28.360
<v Chris Gammell>Well, um, and we have a lot of paperwork too.

00:43:28.360 --> 00:43:40.360
<v Chris Gammell>So after you, um, complete the isolation, you all sign on everyone in the party signs on, um, to an access authority, which, you know, um, it details where the isolations are carried out.

00:43:40.360 --> 00:43:45.360
<v Chris Gammell>So every member of the team knows where the isolation is.

00:43:45.360 --> 00:43:47.360
<v Chris Gammell>So they make sure they're working inside it.

00:43:47.360 --> 00:43:50.360
<v Chris Gammell>And there's a set of visible earths hanging as well.

00:43:50.360 --> 00:43:53.360
<v Chris Gammell>So I was going to ask that where, where is the earth in point?

00:43:53.360 --> 00:43:56.360
<v Dave Jones>Like if you want to isolate the power pole above.

00:43:56.360 --> 00:43:57.360
<v Chris Gammell>Yeah.

00:43:57.360 --> 00:44:05.360
<v Chris Gammell>The hang them on the wires, you go up with your EWP, you test it, and then you hang your earths on those wires and then they come down to the ground and you drive a stake in or use the earth.

00:44:05.360 --> 00:44:06.360
<v Chris Gammell>Oh, okay.

00:44:06.360 --> 00:44:08.360
<v Dave Jones>So you'd physically drive in a stake, right?

00:44:08.360 --> 00:44:09.360
<v Dave Jones>Yeah.

00:44:09.360 --> 00:44:19.360
<v Chris Gammell>Um, or if there's an earthing point that's suitable on the pole or, but, um, you know, the work party can see those earths that are at the fringes of their work site.

00:44:19.360 --> 00:44:21.360
<v Chris Gammell>They can physically see that they're on there.

00:44:21.360 --> 00:44:32.360
<v Chris Gammell>So they know not only have they signed on, seen the isolations take place, seen the testing, but then they can see those earths and know that they're inside that isolation where it's safe.

00:44:32.360 --> 00:44:33.360
<v Dave Jones>Right.

00:44:33.360 --> 00:44:41.360
<v Dave Jones>So, but how, if you're driving a spike in, how would you know that's an adequate ground? Cause that has to do with the soil moisture and the whole.

00:44:41.360 --> 00:44:55.360
<v Chris Gammell>It's more, it's more, it's more the, um, the short circuit protection. Um, so the, the earth has, the earth has three connections on it that run between the phases of the HV. So the three HV phases are bonded together.

00:44:55.360 --> 00:44:57.360
<v Chris Gammell>Oh, got it. Okay. Right.

00:44:57.360 --> 00:45:01.360
<v Dave Jones>And then you have an extra lead that runs down to the ground as well.

00:45:01.360 --> 00:45:05.360
<v Dave Jones>Oh, okay. So really you're doing short circuit protection rather than earth leakage protection.

00:45:05.360 --> 00:45:09.360
<v Dave Jones>Yeah. Got it. Okay. Yep. Sounds good.

00:45:09.360 --> 00:45:16.360
<v Chris Gammell>And our, our, um, our isolation systems. Um, it's funny. I'll tell a bit of a story. I came from Telstra or was telecom back then.

00:45:16.360 --> 00:45:21.360
<v Chris Gammell>Yeah. And, um, you know, it was very digital. I came here and I said, Oh, I helped, you know, as an apprentice, I was like, what are we going to do?

00:45:21.360 --> 00:45:26.360
<v Chris Gammell>How are we going to turn the power off? You know, what app have you got? What, what, what are you going to do?

00:45:26.360 --> 00:45:41.360
<v Chris Gammell>Noob. Yeah. Noob. We got this stick. And I said, what do you mean? You're joking. No, we got a stick and it's literally an extendable stick that's tested. It's insulated and tested regularly. Um, and you reach up and there's plates.

00:45:41.360 --> 00:45:55.360
<v Chris Gammell>So it isn't just a broom handle? No. And they have, you know, under our, under our safety rules, you must look at the date on it when it was last tested. It must be a date. We're very good like that. It's, it's really good and, and it works really well. And yeah, they just put it in.

00:45:55.360 --> 00:46:03.000
<v Chris Gammell>And yeah, they just pull the blades. They're like a knife blade and they just pull the three blades. Um, and they hang down.

00:46:03.000 --> 00:46:10.400
<v Dave Jones>Okay. So you would insert this long, so you would insert this long pole into like a tube on there and then physically pull it.

00:46:10.400 --> 00:46:23.820
<v Chris Gammell>It's got a little ring. You put your hook and you pull the ring down and the blades come out and it de-energizes. And yeah, you've got that open point now. And then the other type, of course we've got, they're called US cells or underslung links.

00:46:23.820 --> 00:46:30.900
<v Chris Gammell>And then we've got our ABSs, which are air brake switches. And they're the ones with the handles. Um, you unlock those and you, and you can open the air.

00:46:30.900 --> 00:46:42.360
<v Chris Gammell>And they're usually what, uh, a, um, an open point, what we call an open point, because if you don't know the, the way the feeders work is it leaves one distribution breaker at the zone sub.

00:46:42.360 --> 00:46:54.880
<v Chris Gammell>It goes out on the poles and wires along the top, the top set of wires is, is the HV and it goes out and, you know, along the way it gets fed into pole mounted transformers, which then produce the LV.

00:46:54.880 --> 00:46:55.880
<v Chris Gammell>It goes out on the pole.

00:46:55.880 --> 00:47:04.680
<v Chris Gammell>But it'll, it'll, it'll get to a point where it's sort of halfway out through the neighborhood and then it'll come back again and go to another breaker.

00:47:05.180 --> 00:47:13.080
<v Chris Gammell>And in between, like, you know, further out in the network, there's, there's that air brake switch in between those two feeders.

00:47:13.160 --> 00:47:18.560
<v Chris Gammell>So the two feeders have an open point where they can be joined if they need to, or it's permanently open.

00:47:18.680 --> 00:47:19.120
<v Dave Jones>Okay.

00:47:19.400 --> 00:47:19.600
<v Dave Jones>Right.

00:47:19.600 --> 00:47:21.160
<v Chris Gammell>It's like called a ring feed.

00:47:22.240 --> 00:47:23.120
<v Dave Jones>Oh yes.

00:47:23.320 --> 00:47:23.900
<v Dave Jones>Yeah, exactly.

00:47:24.080 --> 00:47:26.840
<v Dave Jones>Um, houses, houses can actually be wired.

00:47:26.960 --> 00:47:30.580
<v Dave Jones>Well, I don't know if they can be wired like that in New South Wales in, in the UK.

00:47:30.580 --> 00:47:31.840
<v Dave Jones>Is it that, that does a ring?

00:47:31.840 --> 00:47:38.720
<v Dave Jones>We use a radial, we use a radial system, which goes out from the one point, but you can actually have a ring.

00:47:39.040 --> 00:47:39.480
<v Chris Gammell>Yeah.

00:47:39.660 --> 00:47:49.580
<v Chris Gammell>Not, not all of our distribution networks like that, but, um, you know, there's still lots of radial feeders, but what's cool about that is you can close that open point, which will bond both of those feeders.

00:47:49.580 --> 00:47:56.120
<v Chris Gammell>And then you move somewhere else and you open, um, you open another point.

00:47:56.260 --> 00:48:01.240
<v Chris Gammell>And so you've moved that open point now, and then you go back to where you were before.

00:48:01.240 --> 00:48:02.960
<v Chris Gammell>And now you can open up that other one.

00:48:02.980 --> 00:48:05.420
<v Chris Gammell>And now you've got an isolated section in between.

00:48:06.300 --> 00:48:06.740
<v Dave Jones>Right.

00:48:06.740 --> 00:48:07.840
<v Dave Jones>Does that sort of make sense?

00:48:08.340 --> 00:48:08.620
<v Dave Jones>Nice.

00:48:08.700 --> 00:48:08.840
<v Dave Jones>Yeah.

00:48:08.880 --> 00:48:09.100
<v Dave Jones>Yeah.

00:48:09.100 --> 00:48:09.440
<v Dave Jones>Totally.

00:48:09.600 --> 00:48:10.920
<v Dave Jones>I can actually visualize that.

00:48:10.940 --> 00:48:12.180
<v Chris Gammell>Two isolated points in it.

00:48:12.240 --> 00:48:12.460
<v Chris Gammell>Yeah.

00:48:12.600 --> 00:48:18.320
<v Chris Gammell>So, so initially for the day of switching, you'll get there, you'll call control, get on the switching plan.

00:48:18.320 --> 00:48:19.260
<v Chris Gammell>Everyone's ready to go.

00:48:19.360 --> 00:48:22.220
<v Chris Gammell>You'll close that open point and bond the two feeders together.

00:48:22.500 --> 00:48:25.640
<v Chris Gammell>Then you'll move down the road somewhere and open up another open point.

00:48:25.920 --> 00:48:31.620
<v Chris Gammell>And then from that open point, that'll probably be one of your isolations, one side of your work site.

00:48:31.900 --> 00:48:37.600
<v Chris Gammell>Then you'll move back, you know, through your work site to where you need to go and then open up the next, next one.

00:48:37.600 --> 00:48:40.680
<v Chris Gammell>And now you've got your isolations, your two isolations.

00:48:41.040 --> 00:48:46.000
<v Chris Gammell>But then either side of that still powered up and still back to the two breakers at the zone side.

00:48:46.000 --> 00:48:49.660
<v Dave Jones>Yeah, because you want to minimize the number of people that are without power, right?

00:48:49.660 --> 00:48:49.880
<v Dave Jones>Yeah, disrupt the dots, right.

00:48:49.880 --> 00:48:53.000
<v Dave Jones>So you want to try and choose the optimum area to shut down.

00:48:53.240 --> 00:48:56.680
<v Dave Jones>So how do you do that from like a mapping point of view?

00:48:56.780 --> 00:48:58.200
<v Dave Jones>Oh, we've got a lot of systems, yeah.

00:48:58.200 --> 00:49:00.880
<v Dave Jones>It's digital now.

00:49:01.500 --> 00:49:02.580
<v Dave Jones>It's digital now.

00:49:03.300 --> 00:49:05.500
<v Chris Gammell>And yeah, it's all well mapped.

00:49:05.600 --> 00:49:07.120
<v Chris Gammell>I mean, there's everything you want.

00:49:07.200 --> 00:49:11.540
<v Chris Gammell>There's all the paper maps, but there's also all the digital mapping as well.

00:49:12.120 --> 00:49:12.520
<v Dave Jones>Right.

00:49:12.920 --> 00:49:17.560
<v Dave Jones>And so can the app, so does the app, like if, can the app, is it smart?

00:49:17.640 --> 00:49:19.520
<v Dave Jones>Can it tell you like, okay, we've got a fault here.

00:49:19.520 --> 00:49:24.000
<v Dave Jones>Okay, go over to this pole over here and break that and break this one over here.

00:49:24.000 --> 00:49:26.480
<v Dave Jones>And that minimizes the area that's out?

00:49:26.480 --> 00:49:30.680
<v Chris Gammell>As a switcher, it's up to you to understand the network.

00:49:30.880 --> 00:49:38.620
<v Chris Gammell>And the switching plans for like what we call like a programmed interruption or, you know, an outage that we know we're going to have.

00:49:39.500 --> 00:49:44.580
<v Chris Gammell>Those switching steps are written down and they're passed through a chain of responsibility.

00:49:44.880 --> 00:49:48.500
<v Chris Gammell>And two or three people will look at them before it gets to the control room.

00:49:49.180 --> 00:49:52.520
<v Chris Gammell>And so they'll make sure that the switching steps are correct.

00:49:52.520 --> 00:49:54.540
<v Chris Gammell>You know, you do a close open here.

00:49:54.660 --> 00:49:56.000
<v Chris Gammell>You do an open at this air brake.

00:49:56.100 --> 00:49:57.320
<v Chris Gammell>You pull some underslungs here.

00:49:57.780 --> 00:49:58.580
<v Chris Gammell>You test an earth.

00:49:59.100 --> 00:50:03.240
<v Chris Gammell>The poles you're working on are the poles inside this isolation and so on.

00:50:03.260 --> 00:50:04.900
<v Chris Gammell>So that's all done fairly well.

00:50:05.220 --> 00:50:08.440
<v Chris Gammell>But as for faults in the field, well, that's sort of...

00:50:08.440 --> 00:50:09.380
<v Dave Jones>You have to, yeah.

00:50:09.740 --> 00:50:11.280
<v Chris Gammell>You have to use your best judgment.

00:50:11.440 --> 00:50:13.840
<v Chris Gammell>You might drive along and see what the cause is.

00:50:13.900 --> 00:50:15.000
<v Chris Gammell>It might have been called in.

00:50:15.140 --> 00:50:17.020
<v Chris Gammell>The customers are very good at calling stuff in.

00:50:17.020 --> 00:50:22.240
<v Chris Gammell>The breakers themselves, some of the relays, they actually can look down the line.

00:50:23.080 --> 00:50:25.480
<v Chris Gammell>And I think they use what's called a MOW diagram.

00:50:26.080 --> 00:50:36.500
<v Chris Gammell>It's an expectation of the resistance, the impedance of the feeder for a given length and load.

00:50:36.500 --> 00:50:36.980
<v Chris Gammell>Right.

00:50:36.980 --> 00:50:37.960
<v Dave Jones>And when a fault...

00:50:37.960 --> 00:50:43.580
<v Dave Jones>So they can impedance test the line somehow, sort of like transmission line impedance test, pulse test or something.

00:50:43.820 --> 00:50:45.500
<v Chris Gammell>Yeah, like an echo...

00:50:45.500 --> 00:50:47.120
<v Chris Gammell>What's it called?

00:50:47.260 --> 00:50:48.700
<v Chris Gammell>Time domain reflectometry.

00:50:49.200 --> 00:50:49.660
<v Chris Gammell>You know?

00:50:49.660 --> 00:50:57.120
<v Chris Gammell>But mostly it's the fault data coming out of the relay will sometimes give you a distance.

00:50:58.000 --> 00:51:01.780
<v Chris Gammell>So the distance has been calculated for that feeder under normal conditions.

00:51:02.780 --> 00:51:06.700
<v Chris Gammell>And so a given fault at anywhere along that feeder will produce a certain current.

00:51:07.440 --> 00:51:12.160
<v Chris Gammell>And when that current does come from a fault, you can now say, oh, it must be this distance away.

00:51:12.500 --> 00:51:16.060
<v Chris Gammell>It's probably a face-to-face fault at this distance.

00:51:16.060 --> 00:51:19.160
<v Chris Gammell>And then, you know, the control room can give you a rough idea.

00:51:19.300 --> 00:51:21.560
<v Chris Gammell>You can look at your map and say, oh, that's on such and such road.

00:51:21.620 --> 00:51:22.700
<v Chris Gammell>Let's head out there and have a look.

00:51:23.480 --> 00:51:23.900
<v Chris Gammell>Very into it.

00:51:23.940 --> 00:51:28.100
<v Dave Jones>Like, how do you do load shedding and stuff like that?

00:51:28.280 --> 00:51:33.360
<v Chris Gammell>There's some automated load shedding to prevent, like, a transform.

00:51:33.460 --> 00:51:38.340
<v Chris Gammell>Like, if you knew that the load from the network was going to rise so much that it would eventually,

00:51:38.700 --> 00:51:43.640
<v Chris Gammell>the transform would trip from overcurrent, you'd obviously want to de-energize some of those loads

00:51:43.640 --> 00:51:47.560
<v Chris Gammell>so you didn't get to that point because there's no point knocking everyone off when you just want to.

00:51:47.580 --> 00:51:48.100
<v Dave Jones>Yeah, yeah, right.

00:51:48.320 --> 00:51:53.220
<v Chris Gammell>You know, so they do have some sort of anti-cascade, I guess you'd call it.

00:51:53.280 --> 00:51:54.360
<v Chris Gammell>They do have some load shedding.

00:51:54.840 --> 00:51:57.660
<v Chris Gammell>And it's, you know, they prioritize the feeders, essentially.

00:51:58.440 --> 00:52:01.940
<v Chris Gammell>So, you know, the hospitals and so on are on for the longest.

00:52:02.680 --> 00:52:03.740
<v Dave Jones>They would get the priority.

00:52:03.740 --> 00:52:11.360
<v Dave Jones>And there is apparently some new smart solar inverters that you guys can control.

00:52:12.240 --> 00:52:13.700
<v Dave Jones>You guys can switch them off remotely.

00:52:13.700 --> 00:52:16.040
<v Chris Gammell>The retail section was taken away.

00:52:16.160 --> 00:52:17.720
<v Chris Gammell>We don't do the retail anymore.

00:52:18.160 --> 00:52:22.660
<v Chris Gammell>And so a lot of the metering and that sort of stuff is sort of independent now.

00:52:22.740 --> 00:52:26.900
<v Chris Gammell>And they're the ones coming up with the ideas of, you know, the different load balancing

00:52:26.900 --> 00:52:32.400
<v Chris Gammell>and the pay per time a day use models and all this sort of stuff.

00:52:33.360 --> 00:52:39.800
<v Dave Jones>And there's rumors around that you can adjust the frequency and or the voltage on the line

00:52:39.800 --> 00:52:43.280
<v Dave Jones>to then will automatically disconnect the solar inverters.

00:52:43.340 --> 00:52:47.820
<v Dave Jones>Because all solar inverters are programmed if they meet the, not only the Australian standard,

00:52:47.920 --> 00:52:53.660
<v Dave Jones>but individual state standards, I believe, for voltage and frequency limits.

00:52:53.840 --> 00:52:56.740
<v Dave Jones>And if the grid's outside that voltage limit, they'll shut off.

00:52:56.740 --> 00:52:59.680
<v Dave Jones>And you guys can sort of tweak it.

00:53:00.160 --> 00:53:01.600
<v Dave Jones>That's the rumor that's going around.

00:53:01.740 --> 00:53:03.960
<v Chris Gammell>They can't per se tweak the voltage.

00:53:04.260 --> 00:53:05.700
<v Chris Gammell>The transformers, it's funny.

00:53:06.360 --> 00:53:13.440
<v Chris Gammell>The transformers, when I first started working, I thought there should have been more electronics

00:53:13.440 --> 00:53:14.440
<v Chris Gammell>in the transformers.

00:53:14.580 --> 00:53:15.200
<v Chris Gammell>There should be more smart.

00:53:15.200 --> 00:53:15.860
<v Chris Gammell>Right, no, there's none.

00:53:15.980 --> 00:53:16.540
<v Dave Jones>Is there, right?

00:53:16.580 --> 00:53:17.040
<v Chris Gammell>There's none.

00:53:17.340 --> 00:53:18.060
<v Chris Gammell>And you know what?

00:53:18.140 --> 00:53:23.560
<v Chris Gammell>After seeing a lot of them get hit, yeah, a lot of them get hit by lightning and or, you

00:53:23.560 --> 00:53:24.540
<v Chris Gammell>know, storms and that.

00:53:24.540 --> 00:53:28.400
<v Chris Gammell>I understand because they can just send them back to the factory, drain them out, clean

00:53:28.400 --> 00:53:30.160
<v Chris Gammell>the coils up and they're back in service.

00:53:31.220 --> 00:53:31.620
<v Dave Jones>Right.

00:53:32.100 --> 00:53:33.080
<v Chris Gammell>You know, oil and steel.

00:53:33.080 --> 00:53:36.000
<v Dave Jones>How often do you get a transformer fire?

00:53:36.000 --> 00:53:36.760
<v Dave Jones>Is that common?

00:53:37.220 --> 00:53:38.000
<v Dave Jones>No, not very often.

00:53:38.040 --> 00:53:39.860
<v Chris Gammell>It's actually, yeah, it is.

00:53:39.860 --> 00:53:45.460
<v Chris Gammell>And that's why the times that we have tried to use smarts that they might have.

00:53:46.340 --> 00:53:51.180
<v Chris Gammell>So they have a maximum demand indicator on a lot of these transformers and we read it

00:53:51.180 --> 00:53:51.860
<v Chris Gammell>once a year.

00:53:52.380 --> 00:53:55.920
<v Chris Gammell>And it just shows the maximum amperage that the transformer got to.

00:53:56.780 --> 00:53:57.560
<v Dave Jones>Oh, got it.

00:53:57.640 --> 00:53:59.220
<v Dave Jones>So it's just a peak indicator.

00:53:59.420 --> 00:53:59.700
<v Dave Jones>Okay.

00:53:59.700 --> 00:54:03.180
<v Chris Gammell>Yeah, it's a peak indicator and we just write it down once or twice a year.

00:54:03.460 --> 00:54:08.680
<v Chris Gammell>But we've tried to make versions that are electronic and report back via modem.

00:54:09.340 --> 00:54:13.400
<v Chris Gammell>And of course, you know, they just, sometimes they just can't handle being in the Aussie

00:54:13.400 --> 00:54:17.600
<v Chris Gammell>sun, you know, getting picked on by cockatoos and lightning strikes and that.

00:54:17.740 --> 00:54:17.820
<v Chris Gammell>Yeah.

00:54:18.040 --> 00:54:21.120
<v Dave Jones>Smart electronics than you would in your dumb ass transformers.

00:54:21.340 --> 00:54:21.760
<v Dave Jones>That's right.

00:54:22.080 --> 00:54:23.940
<v Chris Gammell>But our zone subs have gotten more modern.

00:54:24.060 --> 00:54:26.640
<v Chris Gammell>We've gone to Ethernet now for a lot of them.

00:54:26.760 --> 00:54:27.980
<v Chris Gammell>Ethernet connected relays.

00:54:28.460 --> 00:54:30.720
<v Chris Gammell>And we've also gone to SF6 gas.

00:54:31.160 --> 00:54:32.100
<v Chris Gammell>So that's the other thing.

00:54:32.360 --> 00:54:38.360
<v Chris Gammell>Breakers are incredibly, because of the high voltage, an arc can be, you know, 5,000,

00:54:38.480 --> 00:54:40.960
<v Chris Gammell>10,000 degrees, you know, surface of the sun's only 5,000.

00:54:40.960 --> 00:54:42.600
<v Dave Jones>Oh yeah, surface of the sun temperature.

00:54:42.760 --> 00:54:43.420
<v Dave Jones>Yeah, it'll melt everything.

00:54:43.420 --> 00:54:46.160
<v Chris Gammell>Yeah, and so it melts everything, burns the contacts, you know.

00:54:46.160 --> 00:54:48.040
<v Chris Gammell>So we don't want arcing in general.

00:54:48.400 --> 00:54:51.180
<v Chris Gammell>But when the breaker opens, there's going to be some arcing.

00:54:51.180 --> 00:54:53.860
<v Chris Gammell>Because it's pulling two contacts that are energised apart.

00:54:54.340 --> 00:54:56.260
<v Chris Gammell>So there's a number of ways to prevent that.

00:54:56.320 --> 00:54:58.420
<v Chris Gammell>You can blow the arc out with compressed air.

00:54:58.880 --> 00:55:01.380
<v Chris Gammell>That's sort of an old method, but that's quite loud.

00:55:02.060 --> 00:55:06.340
<v Chris Gammell>And the compressors have to run for a bit, so they can't fire multiple times.

00:55:06.860 --> 00:55:09.900
<v Chris Gammell>You know, they have to wait 10 minutes while the compressor fills back up.

00:55:10.320 --> 00:55:13.520
<v Chris Gammell>There's the oil field breakers, and the oil will quench the arc.

00:55:13.520 --> 00:55:15.420
<v Chris Gammell>Then you've got arc shoots.

00:55:15.420 --> 00:55:22.780
<v Chris Gammell>They're like interleaves or sort of steel sheets with a little bit of a gap between them.

00:55:23.160 --> 00:55:27.080
<v Chris Gammell>And the arc magnetises those sheets, which then draws the arc in.

00:55:28.420 --> 00:55:28.980
<v Dave Jones>Interesting.

00:55:29.660 --> 00:55:30.500
<v Chris Gammell>Arc shoots, they're called, yeah.

00:55:30.500 --> 00:55:30.580
<v Chris Gammell>Yeah.

00:55:30.780 --> 00:55:36.220
<v Chris Gammell>And then the latest ones are SF6, sulphur hexafluoride.

00:55:36.960 --> 00:55:40.100
<v Chris Gammell>And that gas does not like to conduct at all.

00:55:40.540 --> 00:55:48.040
<v Chris Gammell>And so you can put it under high pressure, and you can make the bus bars, what in the past might have been the bus bars, might have been two metres apart.

00:55:48.180 --> 00:55:50.220
<v Chris Gammell>Now you can put them, you know, 100 mil apart.

00:55:50.940 --> 00:55:51.140
<v Chris Gammell>Right.

00:55:51.140 --> 00:55:55.160
<v Dave Jones>But if they blow, then you've got to go in and recharge that SF6 gas, do you?

00:55:55.160 --> 00:55:55.560
<v Dave Jones>Yeah, that's right.

00:55:55.620 --> 00:55:58.480
<v Chris Gammell>But they have, you know, of course they've got pressure sensors in them.

00:55:58.680 --> 00:55:59.380
<v Chris Gammell>They're watching everything.

00:55:59.740 --> 00:56:03.360
<v Chris Gammell>But they're also extremely low maintenance as well compared to the oil lines.

00:56:03.880 --> 00:56:04.080
<v Chris Gammell>Yeah.

00:56:04.320 --> 00:56:04.660
<v Dave Jones>Right.

00:56:05.100 --> 00:56:11.400
<v Dave Jones>What is the, speaking of maintenance, what is the most maintained thing on the power lines?

00:56:11.520 --> 00:56:13.100
<v Dave Jones>What, you know, like the suburban?

00:56:13.180 --> 00:56:13.640
<v Dave Jones>The poles.

00:56:13.940 --> 00:56:14.820
<v Chris Gammell>You know, the poles?

00:56:15.100 --> 00:56:15.300
<v Chris Gammell>The poles.

00:56:15.300 --> 00:56:24.500
<v Chris Gammell>Yeah, once every three or four or five years, each pole gets looked at and drilled and tapped and hit with a hammer and checked over.

00:56:24.900 --> 00:56:25.540
<v Dave Jones>Oh, okay.

00:56:25.620 --> 00:56:27.580
<v Dave Jones>So the physical structure of the pole.

00:56:27.580 --> 00:56:27.860
<v Dave Jones>Yeah.

00:56:27.860 --> 00:56:29.140
<v Dave Jones>The poles and the cross arms.

00:56:29.140 --> 00:56:31.760
<v Dave Jones>The actual, right, the actual dead tree.

00:56:32.060 --> 00:56:32.260
<v Chris Gammell>Yeah.

00:56:32.260 --> 00:56:32.800
<v Chris Gammell>That it's all hanging on.

00:56:33.280 --> 00:56:34.720
<v Chris Gammell>Yeah, that it's all hanging on.

00:56:34.900 --> 00:56:35.000
<v Chris Gammell>Right.

00:56:35.020 --> 00:56:35.180
<v Chris Gammell>Yep.

00:56:35.640 --> 00:56:37.060
<v Chris Gammell>And now the insulators will crack.

00:56:37.060 --> 00:56:37.420
<v Dave Jones>I guess that's a plus point.

00:56:37.980 --> 00:56:38.280
<v Dave Jones>Right.

00:56:38.280 --> 00:56:40.940
<v Dave Jones>And the ceramic insulators will crack, right?

00:56:41.140 --> 00:56:43.360
<v Dave Jones>Is that just a manufacturing thing?

00:56:43.640 --> 00:56:43.660
<v Dave Jones>Heat?

00:56:43.660 --> 00:56:45.620
<v Dave Jones>Oh, just the age of them too.

00:56:45.740 --> 00:56:48.600
<v Chris Gammell>We've moved away from ceramics now to polymeric.

00:56:49.420 --> 00:56:52.200
<v Chris Gammell>They're kind of like a silicon, some of them.

00:56:52.440 --> 00:56:53.460
<v Chris Gammell>They're all sort of different.

00:56:53.660 --> 00:56:53.900
<v Dave Jones>Okay.

00:56:54.620 --> 00:57:00.000
<v Chris Gammell>You know, because wires can, you know, or conductors, they can either terminate at the pole or pass overhead.

00:57:00.140 --> 00:57:01.840
<v Chris Gammell>If they pass overhead, they're on pins.

00:57:01.840 --> 00:57:07.580
<v Chris Gammell>But if they terminate on the pole, that's when they'll hang off the polymeric or the thimble insulators, as we call them.

00:57:08.000 --> 00:57:08.840
<v Chris Gammell>A pair of dead ends.

00:57:08.840 --> 00:57:17.700
<v Chris Gammell>They're like a spirally wound piece of metal that grips the conductor and then bonds over the top.

00:57:17.700 --> 00:57:21.300
<v Chris Gammell>But there's a lot of different gear out there that you'll see.

00:57:21.420 --> 00:57:28.340
<v Chris Gammell>But they're moving towards, as you know, because you can't just trial things wholesale.

00:57:28.720 --> 00:57:30.160
<v Chris Gammell>You don't want problems, you know.

00:57:30.660 --> 00:57:31.160
<v Chris Gammell>No, exactly.

00:57:31.160 --> 00:57:31.720
<v Chris Gammell>You want your roll stuff out.

00:57:31.800 --> 00:57:32.540
<v Chris Gammell>You want it to last.

00:57:32.540 --> 00:57:37.980
<v Chris Gammell>Because most of this equipment, once it's installed, it's in there for 10, 15, 20, 30 years.

00:57:38.620 --> 00:57:39.020
<v Dave Jones>Right.

00:57:39.560 --> 00:57:39.760
<v Dave Jones>Yep.

00:57:39.760 --> 00:57:40.720
<v Dave Jones>It's crazy.

00:57:41.340 --> 00:57:41.500
<v Chris Gammell>Yeah.

00:57:41.680 --> 00:57:46.880
<v Dave Jones>Where would the cost, I mean, this is probably company confidential, but where is the biggest cost base?

00:57:47.380 --> 00:57:48.900
<v Dave Jones>Is it generation?

00:57:49.160 --> 00:57:50.200
<v Dave Jones>Is it transmission?

00:57:50.400 --> 00:57:51.060
<v Dave Jones>Is it maintenance?

00:57:51.240 --> 00:57:51.840
<v Dave Jones>Is it personnel?

00:57:52.320 --> 00:57:52.520
<v Chris Gammell>Is it?

00:57:52.520 --> 00:58:00.720
<v Chris Gammell>We probably don't pay for generation because the electrical energy is sold by the retail side.

00:58:01.480 --> 00:58:08.920
<v Chris Gammell>So they're charging their customers and they're buying the electricity off the generator to do that, I guess.

00:58:08.920 --> 00:58:12.680
<v Chris Gammell>So for us, it's going to be, oh, I'm not sure.

00:58:12.800 --> 00:58:15.820
<v Chris Gammell>There's a fair bit in the vegetation maintenance space.

00:58:16.300 --> 00:58:16.700
<v Dave Jones>Okay.

00:58:16.700 --> 00:58:19.940
<v Chris Gammell>Keeping trees clear of wires.

00:58:20.400 --> 00:58:22.320
<v Dave Jones>Lopping trees and stuff like that.

00:58:22.420 --> 00:58:27.620
<v Dave Jones>Do you guys just call in any tree lopper or do you guys have your own specialized tree loppers?

00:58:27.960 --> 00:58:28.560
<v Chris Gammell>Yeah, we have.

00:58:28.720 --> 00:58:37.300
<v Chris Gammell>We usually set up some contracts with them and, you know, we have a couple of different major companies that look after us and trim the network.

00:58:38.220 --> 00:58:46.600
<v Chris Gammell>You know, customers, there are certain times that customers just can't really work on trees near the network, obviously, because it's just highly unsafe.

00:58:47.480 --> 00:58:53.260
<v Chris Gammell>And so, you know, there's certain work there that we have to do, you know, for the customers, for the councils and so on.

00:58:53.640 --> 00:58:55.360
<v Chris Gammell>So, yeah, we have an envelope.

00:58:55.660 --> 00:58:59.320
<v Chris Gammell>It's a set of clearances that the trees need to stay outside of.

00:59:00.460 --> 00:59:08.940
<v Chris Gammell>And so there's a, you know, they trim them back with a little bit of a regrowth factor and then trim them, you know, annually, semi-annually every couple of years, depending on the area.

00:59:10.640 --> 00:59:14.420
<v Chris Gammell>But, yeah, cross arms, you know, they used to be timber.

00:59:14.420 --> 00:59:18.800
<v Chris Gammell>Now we're getting, you know, ones that we've trialed metal ones.

00:59:18.960 --> 00:59:21.080
<v Chris Gammell>We've trialed composite ones.

00:59:21.540 --> 00:59:24.080
<v Chris Gammell>Yeah, we've trialed every kind of thing.

00:59:24.200 --> 00:59:27.900
<v Chris Gammell>There's metal poles, concrete poles, timber poles, composite poles.

00:59:28.120 --> 00:59:31.960
<v Chris Gammell>And they all have their sort of benefits and disadvantages.

00:59:32.500 --> 00:59:33.480
<v Dave Jones>Power factor correction.

00:59:34.080 --> 00:59:34.540
<v Chris Gammell>Ah, yes.

00:59:34.860 --> 00:59:36.340
<v Dave Jones>How much of that is on the network?

00:59:36.560 --> 00:59:38.500
<v Dave Jones>Like how many and what types and where?

00:59:38.500 --> 00:59:41.140
<v Chris Gammell>From our point of view, we don't have a lot of it.

00:59:41.560 --> 00:59:43.360
<v Chris Gammell>The, we, well, we sort of do.

00:59:43.520 --> 00:59:52.720
<v Chris Gammell>If you have a load over a certain amount, it's up to you to make sure that you have power factor correction in the building.

00:59:52.980 --> 00:59:53.380
<v Dave Jones>Right.

00:59:53.440 --> 00:59:59.320
<v Dave Jones>So if you're a giant factory with massive motors going, you have to install, legally you have to install your own.

00:59:59.420 --> 01:00:02.040
<v Chris Gammell>Well, you'll be, you'll get charged more from the retailer.

01:00:02.040 --> 01:00:03.160
<v Dave Jones>Oh, you get charged a lot more.

01:00:03.240 --> 01:00:03.440
<v Dave Jones>Okay.

01:00:03.440 --> 01:00:05.080
<v Chris Gammell>Based on your power factor.

01:00:05.240 --> 01:00:09.200
<v Chris Gammell>So, you know, for us home punters, we don't, we don't get charged power factor.

01:00:09.380 --> 01:00:09.480
<v Chris Gammell>No.

01:00:09.820 --> 01:00:10.220
<v Chris Gammell>That's right.

01:00:10.320 --> 01:00:12.860
<v Chris Gammell>And it's not even monitored in the meter in general.

01:00:13.220 --> 01:00:15.020
<v Chris Gammell>The electronic ones probably can, but.

01:00:15.140 --> 01:00:17.300
<v Dave Jones>The newer smart ones do, I think.

01:00:17.520 --> 01:00:19.040
<v Dave Jones>But we still don't pay for it.

01:00:19.120 --> 01:00:19.240
<v Dave Jones>Yeah.

01:00:19.640 --> 01:00:21.240
<v Chris Gammell>But the bigger guys do.

01:00:21.380 --> 01:00:27.680
<v Chris Gammell>And so they'll have a power factor correction cubicle, which just, I think it's just a cap, cap bank that switches in and out.

01:00:27.680 --> 01:00:42.540
<v Chris Gammell>But where, where we do, where they sometimes have it in an infrastructure sense, like inside a zone sub is there might be a high voltage customer that'll have a feeder that goes to say an aluminum smelter.

01:00:42.940 --> 01:00:44.540
<v Chris Gammell>Or a glass smelter.

01:00:44.540 --> 01:00:44.780
<v Chris Gammell>Yes, of course.

01:00:44.940 --> 01:00:45.940
<v Dave Jones>Massive power demand.

01:00:45.940 --> 01:00:52.660
<v Chris Gammell>They, they dip these electrodes, 11 KV electrodes directly into the bauxite.

01:00:53.340 --> 01:00:59.140
<v Chris Gammell>And, you know, just the power that it draws in a split second from, from the system is crazy.

01:00:59.140 --> 01:01:02.000
<v Chris Gammell>So they have to design, I think they call it a reactor.

01:01:02.260 --> 01:01:04.140
<v Chris Gammell>It's basically a big coil choke.

01:01:04.140 --> 01:01:06.520
<v Chris Gammell>I think, you know, that kind of smooths the power.

01:01:06.520 --> 01:01:06.300
<v Speaker ?>I was going to ask.

01:01:06.440 --> 01:01:06.540
<v Chris Gammell>Yeah.

01:01:06.540 --> 01:01:10.380
<v Dave Jones>Because most power factor correction would be capacitive, right?

01:01:10.500 --> 01:01:13.620
<v Dave Jones>I was going to talk about, are there any inductive power correction?

01:01:13.620 --> 01:01:14.620
<v Dave Jones>Yeah, look, I'm not sure, but.

01:01:14.620 --> 01:01:16.860
<v Dave Jones>That would be a case where they use it, right?

01:01:17.540 --> 01:01:17.880
<v Chris Gammell>Yeah.

01:01:18.120 --> 01:01:18.380
<v Chris Gammell>Yeah.

01:01:18.600 --> 01:01:22.500
<v Chris Gammell>It's by, it would be by exception, you know, for special projects.

01:01:22.500 --> 01:01:27.580
<v Chris Gammell>But I think, you know, the average, you know, home device these days, it's pretty good.

01:01:27.580 --> 01:01:39.100
<v Chris Gammell>Like, you know, as an electrician, I remember working as an apprentice and definitely if, you know, be pulling a fluorescent light apart to fix it for the customer and the capacitor's blown.

01:01:39.100 --> 01:01:45.400
<v Chris Gammell>And it's just in parallel or whatever, you just pull it out, you know, the power factor correction, away you go.

01:01:45.900 --> 01:01:47.780
<v Chris Gammell>But you don't do that in an office.

01:01:47.940 --> 01:01:52.740
<v Chris Gammell>You don't buy the non-power factor corrected lights when you've got a thousand of them to put up in a.

01:01:52.920 --> 01:01:53.560
<v Dave Jones>Yeah, exactly.

01:01:54.040 --> 01:01:55.500
<v Chris Gammell>You know, you'll be paying for it.

01:01:56.040 --> 01:01:56.200
<v Dave Jones>Yeah.

01:01:56.280 --> 01:02:01.080
<v Dave Jones>So the big question, big question, everyone wants to know, of course, is what meter do you guys use?

01:02:01.640 --> 01:02:05.980
<v Dave Jones>If you're a linesman, if you're out there, out in the field, which meter is there?

01:02:05.980 --> 01:02:07.100
<v Dave Jones>Are there approved meters?

01:02:07.580 --> 01:02:08.560
<v Chris Gammell>Yeah, oh, absolutely.

01:02:08.680 --> 01:02:10.000
<v Chris Gammell>We used to use the T140.

01:02:10.960 --> 01:02:15.780
<v Chris Gammell>It was a fluke and it's a style with a probe at one end.

01:02:15.780 --> 01:02:19.940
<v Chris Gammell>So it's not like a traditional rotary dial type or anything like that or push button.

01:02:20.200 --> 01:02:21.140
<v Chris Gammell>It's a single.

01:02:21.480 --> 01:02:23.360
<v Chris Gammell>Well, they used to use test lamps, Dave.

01:02:23.960 --> 01:02:24.500
<v Dave Jones>Oh, yeah.

01:02:24.540 --> 01:02:25.940
<v Dave Jones>A pair of lamps.

01:02:26.360 --> 01:02:27.260
<v Dave Jones>Yeah, no worries.

01:02:27.260 --> 01:02:32.040
<v Chris Gammell>Obviously, with all our testing, we're pretty smart around it.

01:02:32.120 --> 01:02:34.980
<v Chris Gammell>We test before and after.

01:02:34.980 --> 01:02:37.880
<v Chris Gammell>So you make sure your meter is working correctly.

01:02:38.620 --> 01:02:39.200
<v Chris Gammell>All right.

01:02:39.200 --> 01:02:40.440
<v Chris Gammell>So it's actually reading.

01:02:40.580 --> 01:02:43.840
<v Chris Gammell>Then you do your test and you prove your isolation.

01:02:43.840 --> 01:02:45.720
<v Chris Gammell>Then you test your meter again.

01:02:46.300 --> 01:02:49.860
<v Chris Gammell>So even with a set of test lamps, theoretically, you shouldn't have a problem.

01:02:50.480 --> 01:02:58.060
<v Chris Gammell>But if you fail to test again and you've got a blown bulb in your test lamps, then it wasn't going to pick up your test properly.

01:02:58.240 --> 01:02:58.520
<v Chris Gammell>Exactly.

01:02:59.220 --> 01:03:01.340
<v Chris Gammell>So we moved away from that.

01:03:01.340 --> 01:03:02.720
<v Chris Gammell>But it's a similar thing.

01:03:02.780 --> 01:03:08.820
<v Chris Gammell>It has the two probes because you've got to imagine the guy might be on a platform or hanging off a ladder in his belt.

01:03:08.980 --> 01:03:10.640
<v Chris Gammell>And he's reaching above his head.

01:03:10.720 --> 01:03:12.500
<v Chris Gammell>And he's going from phase to phase.

01:03:12.560 --> 01:03:13.660
<v Chris Gammell>And this is only LV.

01:03:13.660 --> 01:03:16.580
<v Chris Gammell>And so it's a Fluke T140.

01:03:16.580 --> 01:03:19.180
<v Dave Jones>I've got it open right here.

01:03:19.240 --> 01:03:22.380
<v Dave Jones>And for those curious, it's a Cat 4, only 600 volts.

01:03:22.500 --> 01:03:23.740
<v Dave Jones>Cat 4, 600 volts.

01:03:24.060 --> 01:03:25.540
<v Dave Jones>Cat 3, 690 volts.

01:03:25.640 --> 01:03:27.460
<v Dave Jones>So it's not as good as it gets.

01:03:27.500 --> 01:03:30.020
<v Dave Jones>You can actually get Cat 4,000 volts these days.

01:03:30.420 --> 01:03:32.040
<v Dave Jones>So it's the form factor.

01:03:32.580 --> 01:03:33.440
<v Dave Jones>It's the form factor.

01:03:33.560 --> 01:03:34.440
<v Dave Jones>It's the form factor.

01:03:34.440 --> 01:03:37.940
<v Chris Gammell>We have – I'm going to get in trouble because the guys are going to roast me.

01:03:38.000 --> 01:03:40.300
<v Chris Gammell>I'm sure we've moved away from that one now.

01:03:40.580 --> 01:03:41.200
<v Chris Gammell>We've moved again.

01:03:41.200 --> 01:03:41.380
<v Chris Gammell>Okay.

01:03:41.620 --> 01:03:46.380
<v Chris Gammell>But I know, for example, in the Zone subs, they use a higher Cat rated one again.

01:03:47.100 --> 01:03:47.540
<v Dave Jones>Right.

01:03:47.540 --> 01:03:51.600
<v Chris Gammell>Because you do have the potentials there for, you know, 11 kV.

01:03:52.000 --> 01:03:52.560
<v Chris Gammell>I wouldn't know.

01:03:52.620 --> 01:03:53.500
<v Chris Gammell>But I can get back to you.

01:03:54.200 --> 01:03:54.560
<v Dave Jones>Yeah.

01:03:54.680 --> 01:03:55.620
<v Dave Jones>Get back to me, please.

01:03:55.680 --> 01:03:56.520
<v Dave Jones>I'll put it in the comments.

01:03:56.700 --> 01:03:59.680
<v Chris Gammell>When we do the high voltage, there's special gear there.

01:03:59.760 --> 01:04:02.060
<v Chris Gammell>We have what's called a Modiwark or Modiwark.

01:04:02.180 --> 01:04:03.020
<v Chris Gammell>It's the brand.

01:04:03.540 --> 01:04:06.000
<v Chris Gammell>And it's a – it comes with a little hand test.

01:04:06.260 --> 01:04:07.080
<v Chris Gammell>And it's a feel.

01:04:07.080 --> 01:04:08.220
<v Dave Jones>How do you pronounce that?

01:04:08.420 --> 01:04:08.760
<v Dave Jones>Modi?

01:04:09.120 --> 01:04:11.960
<v Chris Gammell>M-O-D-I-W-A-R-K?

01:04:12.360 --> 01:04:13.440
<v Chris Gammell>Maybe Modiwark?

01:04:14.220 --> 01:04:15.060
<v Chris Gammell>Modiwark kit.

01:04:15.200 --> 01:04:15.460
<v Dave Jones>Okay.

01:04:15.740 --> 01:04:16.140
<v Dave Jones>Yeah.

01:04:16.140 --> 01:04:18.220
<v Chris Gammell>So, you know, there's a lot of brands.

01:04:18.220 --> 01:04:18.560
<v Chris Gammell>Oh, I see.

01:04:18.680 --> 01:04:18.900
<v Chris Gammell>Yeah.

01:04:19.020 --> 01:04:24.240
<v Chris Gammell>Some of them are non-contact testers because, you know, with high voltage ABC bundled,

01:04:24.440 --> 01:04:27.520
<v Chris Gammell>aerial bundle conductor, it's obviously insulated with XLPE.

01:04:27.720 --> 01:04:29.380
<v Chris Gammell>You can't pierce it with your tester.

01:04:29.940 --> 01:04:33.940
<v Chris Gammell>So you need to, you know, just check on the outside of the cable with a field tester.

01:04:33.940 --> 01:04:39.060
<v Chris Gammell>A lot like those voltage pens, which, by the way, we do not use those voltage pens.

01:04:39.340 --> 01:04:39.480
<v Dave Jones>No.

01:04:39.600 --> 01:04:44.540
<v Dave Jones>Well, this is basically a high voltage professional version of those voltage pens, right?

01:04:44.540 --> 01:04:47.880
<v Dave Jones>So it is a non-contact tester.

01:04:48.260 --> 01:04:48.460
<v Chris Gammell>Yep.

01:04:48.640 --> 01:04:53.480
<v Chris Gammell>And you push that up on the pole because, obviously, you can't get close enough on the stick, sorry,

01:04:53.540 --> 01:04:57.780
<v Chris Gammell>because, obviously, you're not going to be within clearances or work on high voltage while it's energized.

01:04:57.780 --> 01:04:58.100
<v Chris Gammell>Right.

01:04:58.100 --> 01:05:02.240
<v Chris Gammell>So you test from the ground generally or in a bucket, or EWP, sorry.

01:05:02.380 --> 01:05:05.420
<v Chris Gammell>You might test from in there nearby, sort of push it near the mains.

01:05:05.560 --> 01:05:08.780
<v Chris Gammell>You'll test each of the phases and then you'll test the meter itself.

01:05:09.080 --> 01:05:15.740
<v Chris Gammell>It comes with a little handheld thing that you push a button and it creates a field and you hold it on there and it beeps.

01:05:15.820 --> 01:05:16.220
<v Chris Gammell>Interesting.

01:05:16.580 --> 01:05:16.780
<v Dave Jones>Yeah.

01:05:17.100 --> 01:05:17.920
<v Dave Jones>Specialized bit of kit.

01:05:18.140 --> 01:05:18.620
<v Chris Gammell>Yeah, of course.

01:05:18.680 --> 01:05:18.940
<v Chris Gammell>It is.

01:05:19.020 --> 01:05:19.840
<v Chris Gammell>We've got a few of those.

01:05:19.840 --> 01:05:26.540
<v Chris Gammell>We've got clamp tong amateurs as well that, you know, you can do 1,200 amps at, you know, 132 kV.

01:05:27.060 --> 01:05:27.640
<v Dave Jones>Yeah, right.

01:05:27.780 --> 01:05:28.260
<v Dave Jones>Yeah, yeah.

01:05:28.300 --> 01:05:28.840
<v Chris Gammell>Push them up.

01:05:28.840 --> 01:05:30.080
<v Dave Jones>But I assume you wouldn't.

01:05:30.240 --> 01:05:33.740
<v Dave Jones>Would you use a current clamp that often or is that?

01:05:34.060 --> 01:05:34.780
<v Chris Gammell>Not really.

01:05:35.000 --> 01:05:38.680
<v Chris Gammell>In the zone subs when you're doing, they're called protection technicians.

01:05:39.160 --> 01:05:40.520
<v Chris Gammell>I know you get a lot of people listening.

01:05:40.520 --> 01:05:48.980
<v Chris Gammell>So if there's any young budding engineers out there, have a look at, you know, employment in this field because it can be really fascinating.

01:05:49.100 --> 01:05:57.880
<v Chris Gammell>But we do a lot of current measurement in the zone subs because all of the protection equipment, the breakers and everything, that's what they use to trip.

01:05:58.400 --> 01:06:07.780
<v Chris Gammell>They even have what we call differential protection schemes, which is where you ship a portion of the current you're sending on an overhead pilot wire to the far end.

01:06:08.860 --> 01:06:10.060
<v Chris Gammell>Oh, really?

01:06:10.060 --> 01:06:10.580
<v Chris Gammell>Yeah.

01:06:10.720 --> 01:06:13.160
<v Chris Gammell>And that current holds a relay open.

01:06:13.680 --> 01:06:16.600
<v Chris Gammell>And the moment that current stops, that relay drops.

01:06:17.540 --> 01:06:19.900
<v Chris Gammell>So it's like, I've sent you this.

01:06:20.140 --> 01:06:21.840
<v Chris Gammell>If you don't receive it, you need to trip.

01:06:21.860 --> 01:06:22.160
<v Chris Gammell>Yeah.

01:06:22.760 --> 01:06:23.060
<v Chris Gammell>Yeah.

01:06:23.180 --> 01:06:24.580
<v Chris Gammell>And that was very old school.

01:06:24.660 --> 01:06:32.320
<v Chris Gammell>And that's really just a set of CTs that then, you know, send that current over a pilot wire to the far end relay.

01:06:33.280 --> 01:06:35.060
<v Dave Jones>Nowadays, it'd be done with comms, right?

01:06:35.240 --> 01:06:35.680
<v Dave Jones>It is.

01:06:35.900 --> 01:06:37.180
<v Dave Jones>And it's optic fibre now.

01:06:37.500 --> 01:06:37.600
<v Chris Gammell>Yep.

01:06:37.780 --> 01:06:38.200
<v Chris Gammell>Right.

01:06:38.200 --> 01:06:38.820
<v Dave Jones>Multi-stream optic fibre.

01:06:38.820 --> 01:06:39.720
<v Dave Jones>Newfangled stuff.

01:06:39.720 --> 01:06:40.060
<v Dave Jones>Yeah.

01:06:40.160 --> 01:06:40.380
<v Dave Jones>Yeah.

01:06:40.740 --> 01:06:41.140
<v Dave Jones>Boo.

01:06:41.660 --> 01:06:43.320
<v Chris Gammell>We've used radio a little bit.

01:06:43.560 --> 01:06:45.580
<v Chris Gammell>Look, nothing beats the physicality.

01:06:45.660 --> 01:06:48.060
<v Chris Gammell>All the breakers and that, they're all physically wired.

01:06:48.780 --> 01:06:50.320
<v Chris Gammell>Every single one of them, just about.

01:06:51.020 --> 01:06:57.100
<v Chris Gammell>They were actually a bit shy when they put their first sort of Ethernet style.

01:06:57.320 --> 01:06:58.100
<v Dave Jones>Yeah, I bet.

01:06:58.100 --> 01:07:01.900
<v Chris Gammell>They're a bit nervous about this because it's a bit newfangled for us, you know.

01:07:02.100 --> 01:07:02.960
<v Dave Jones>Yeah, exactly.

01:07:03.960 --> 01:07:07.360
<v Chris Gammell>Liability's important, but protection is, you know, paramount.

01:07:07.860 --> 01:07:09.900
<v Chris Gammell>You know, safety's a rule.

01:07:09.900 --> 01:07:11.580
<v Chris Gammell>Do you know the rule?

01:07:11.580 --> 01:07:13.460
<v Chris Gammell>Is it I-Z, I-B, I-N?

01:07:14.180 --> 01:07:15.940
<v Chris Gammell>I-Z's got to be greater than I-B.

01:07:16.060 --> 01:07:16.820
<v Chris Gammell>He's got to be greater than I.

01:07:16.900 --> 01:07:19.940
<v Chris Gammell>It's in the AS3000, which is our electrical safety.

01:07:20.080 --> 01:07:22.420
<v Chris Gammell>That's the electrical rules in Australia for an electrician.

01:07:22.420 --> 01:07:22.580
<v Dave Jones>Oh, okay.

01:07:22.740 --> 01:07:22.920
<v Dave Jones>Yep.

01:07:23.000 --> 01:07:24.700
<v Chris Gammell>I-Z is the impedance of the cable.

01:07:25.300 --> 01:07:25.560
<v Dave Jones>Yep.

01:07:25.560 --> 01:07:30.320
<v Chris Gammell>I-B is the breaker current.

01:07:30.800 --> 01:07:33.680
<v Chris Gammell>And I-N is your expected normal load.

01:07:34.100 --> 01:07:35.020
<v Chris Gammell>I think this is right.

01:07:35.340 --> 01:07:39.740
<v Chris Gammell>So, you know, the cable's got to have the highest current carrying capacity.

01:07:40.700 --> 01:07:42.300
<v Chris Gammell>And then the breaker and then the load.

01:07:42.540 --> 01:07:47.220
<v Chris Gammell>So the breaker should trip before the cable burns.

01:07:48.100 --> 01:07:48.500
<v Dave Jones>Correct.

01:07:48.620 --> 01:07:49.440
<v Dave Jones>That's the whole point.

01:07:49.700 --> 01:07:50.560
<v Chris Gammell>That's the whole.

01:07:50.640 --> 01:07:52.940
<v Chris Gammell>It says in the front, it's the first paragraph, I think.

01:07:53.820 --> 01:07:54.560
<v Dave Jones>Right, is it?

01:07:54.560 --> 01:07:57.080
<v Dave Jones>I see this is something that I don't generally know.

01:07:57.080 --> 01:08:04.300
<v Dave Jones>But I do know that the circuit breaker in your house is not designed to protect your products that you plug in.

01:08:04.420 --> 01:08:07.120
<v Dave Jones>It's designed to protect the wiring from catching on fire.

01:08:07.500 --> 01:08:09.380
<v Chris Gammell>You've got a 20-amp cable.

01:08:09.560 --> 01:08:13.020
<v Chris Gammell>You can't put anything bigger than, you know, an 18 or 19 or 20-amp breaker.

01:08:13.920 --> 01:08:15.020
<v Chris Gammell>I-N could be higher.

01:08:15.120 --> 01:08:19.120
<v Chris Gammell>You can draw 40 amps, but you're just going to trip your breaker all the time and it's going to be a nuisance.

01:08:19.500 --> 01:08:22.840
<v Chris Gammell>But, yeah, I-Z's got to be bigger than I-B.

01:08:22.840 --> 01:08:25.460
<v Dave Jones>I've never heard it explained like that before.

01:08:25.460 --> 01:08:26.640
<v Dave Jones>But, yes, that makes sense.

01:08:26.640 --> 01:08:31.800
<v Chris Gammell>I think it's in, when you train as an electrician, I think it's in that AS3000, the Australian standard.

01:08:32.040 --> 01:08:34.540
<v Chris Gammell>And that's our wiring standards for domestic dwellings.

01:08:35.000 --> 01:08:37.840
<v Chris Gammell>There's another one that people might enjoy looking up.

01:08:37.840 --> 01:08:41.680
<v Chris Gammell>And that is the Australian, the service rules.

01:08:42.720 --> 01:08:50.120
<v Chris Gammell>And the service rules, the New South Wales service rules, they're the ones that sort of, it's in between your house and the street.

01:08:50.540 --> 01:08:55.280
<v Chris Gammell>You know, what cable you should run from your board out to the street.

01:08:55.920 --> 01:08:56.800
<v Chris Gammell>You know, what size conduit.

01:08:56.800 --> 01:08:57.420
<v Chris Gammell>Next level up.

01:08:57.420 --> 01:09:01.540
<v Chris Gammell>How high your service mains need to be above a driveway.

01:09:01.840 --> 01:09:03.260
<v Chris Gammell>How high above an awning.

01:09:03.960 --> 01:09:04.940
<v Chris Gammell>What size conductor.

01:09:05.120 --> 01:09:05.300
<v Chris Gammell>Got it.

01:09:05.300 --> 01:09:05.540
<v Chris Gammell>That's it.

01:09:05.660 --> 01:09:08.040
<v Chris Gammell>New South Wales service and installation rules.

01:09:08.480 --> 01:09:09.520
<v Dave Jones>There you go.

01:09:09.600 --> 01:09:09.740
<v Chris Gammell>Yeah.

01:09:10.360 --> 01:09:11.260
<v Chris Gammell>It's another document.

01:09:11.520 --> 01:09:12.600
<v Dave Jones>Fun bedtime reading.

01:09:12.760 --> 01:09:12.900
<v Dave Jones>Yeah.

01:09:12.900 --> 01:09:16.200
<v Dave Jones>This is great.

01:09:17.060 --> 01:09:18.740
<v Dave Jones>Oh, thank you very much, Toby.

01:09:18.940 --> 01:09:20.520
<v Dave Jones>Our amp power is unfortunately up.

01:09:20.600 --> 01:09:23.560
<v Dave Jones>We can talk about this interesting stuff all day.

01:09:23.680 --> 01:09:25.800
<v Dave Jones>But that flew by.

01:09:26.220 --> 01:09:27.620
<v Dave Jones>That is great stuff.

01:09:27.920 --> 01:09:30.520
<v Dave Jones>Which we just don't, because we have no idea about this.

01:09:30.640 --> 01:09:33.820
<v Dave Jones>You know, just as a general, you know, engineering nerd.

01:09:34.020 --> 01:09:35.660
<v Dave Jones>We just, no, we just take it for granted.

01:09:35.660 --> 01:09:38.960
<v Chris Gammell>Yeah, we use the power that comes in to the house and that's it.

01:09:39.020 --> 01:09:40.520
<v Chris Gammell>We know there's generators out there.

01:09:40.520 --> 01:09:45.140
<v Chris Gammell>We know there's zone subs, but there is quite a bit of engineering that goes into it.

01:09:45.360 --> 01:09:46.020
<v Chris Gammell>There really is.

01:09:46.520 --> 01:09:46.700
<v Dave Jones>Yeah.

01:09:46.820 --> 01:09:47.060
<v Dave Jones>Fantastic.

01:09:47.120 --> 01:09:49.860
<v Dave Jones>I'd love to get like a tour of one one day, you know.

01:09:49.880 --> 01:09:50.380
<v Dave Jones>Let me see.

01:09:51.120 --> 01:09:51.560
<v Chris Gammell>Yeah.

01:09:51.620 --> 01:09:52.200
<v Chris Gammell>I'm not sure.

01:09:52.360 --> 01:09:54.140
<v Chris Gammell>That's probably something we've never really done.

01:09:54.240 --> 01:09:59.040
<v Chris Gammell>But I know there's some great zone subs that you'd really be fascinated by.

01:09:59.160 --> 01:10:02.720
<v Chris Gammell>And there's a lot of associated systems too that we didn't even talk about.

01:10:02.960 --> 01:10:06.380
<v Chris Gammell>Like the frequency injection for the hot water systems, you know.

01:10:06.400 --> 01:10:07.280
<v Dave Jones>Oh, yes, of course.

01:10:07.300 --> 01:10:08.700
<v Dave Jones>The street lighting systems.

01:10:08.700 --> 01:10:09.340
<v Dave Jones>Yeah, yeah.

01:10:09.340 --> 01:10:13.740
<v Chris Gammell>You know, there's a lot of stuff in those zone subs that you don't even see.

01:10:13.880 --> 01:10:15.840
<v Chris Gammell>And it's more electronics focused too.

01:10:16.260 --> 01:10:20.140
<v Dave Jones>Yes, which is basically comms over power line for those that don't know.

01:10:20.240 --> 01:10:24.300
<v Dave Jones>They send like the hot water thing was a one or two kilohertz signal.

01:10:24.580 --> 01:10:25.200
<v Dave Jones>Yeah, that's right.

01:10:25.200 --> 01:10:27.680
<v Dave Jones>Which was actually modulated over the power line.

01:10:27.800 --> 01:10:29.040
<v Chris Gammell>Sometimes you'll hear it.

01:10:29.100 --> 01:10:30.420
<v Chris Gammell>If you've got a fan running.

01:10:30.460 --> 01:10:30.680
<v Chris Gammell>Yes.

01:10:30.680 --> 01:10:32.240
<v Chris Gammell>You'll sometimes hear it in the motor windings.

01:10:32.600 --> 01:10:32.800
<v Dave Jones>Yep.

01:10:32.960 --> 01:10:34.540
<v Dave Jones>Or you'll see it on your oscilloscope.

01:10:34.540 --> 01:10:37.100
<v Dave Jones>I see it pop up in the lab all the bloody time.

01:10:37.260 --> 01:10:39.660
<v Dave Jones>I'm taking some sort of mains measurement.

01:10:39.880 --> 01:10:41.360
<v Dave Jones>And, you know, there's my 50 hertz waveform.

01:10:41.460 --> 01:10:43.840
<v Dave Jones>And that pops this little modulated bloody sine wave on top of it.

01:10:43.860 --> 01:10:46.000
<v Chris Gammell>Yeah, up to seven volts or something sometimes too.

01:10:46.040 --> 01:10:46.200
<v Chris Gammell>Yeah.

01:10:46.200 --> 01:10:46.380
<v Chris Gammell>Yeah.

01:10:46.380 --> 01:10:47.540
<v Chris Gammell>It just sticks out like a dog's eye leg.

01:10:47.540 --> 01:10:48.260
<v Chris Gammell>You can see the injection.

01:10:48.640 --> 01:10:48.800
<v Chris Gammell>Yeah.

01:10:48.860 --> 01:10:51.300
<v Chris Gammell>At the other end, there's a big cabinet that controls it.

01:10:51.340 --> 01:10:57.540
<v Chris Gammell>But then to inject it, there's these toroidal transformers and all this crazy gear.

01:10:57.700 --> 01:11:00.240
<v Chris Gammell>And it just looks incredible just to inject it on.

01:11:00.300 --> 01:11:02.360
<v Chris Gammell>Because you've got to inject it onto the 11 kV.

01:11:03.100 --> 01:11:06.140
<v Dave Jones>And it's a very low impedance line you're injecting onto as well.

01:11:06.260 --> 01:11:07.900
<v Dave Jones>It's like, yeah, it's got to be grunty to.

01:11:08.600 --> 01:11:08.920
<v Chris Gammell>Yeah.

01:11:09.320 --> 01:11:09.520
<v Chris Gammell>Yeah.

01:11:09.880 --> 01:11:10.280
<v Dave Jones>Wow.

01:11:11.460 --> 01:11:12.300
<v Dave Jones>Fascinating stuff.

01:11:13.000 --> 01:11:13.360
<v Dave Jones>All right.

01:11:13.440 --> 01:11:14.560
<v Dave Jones>Well, thank you very much, Toby.

01:11:14.820 --> 01:11:15.360
<v Dave Jones>You're welcome.

01:11:15.360 --> 01:11:18.380
<v Dave Jones>Where can people catch you?

01:11:18.960 --> 01:11:20.040
<v Chris Gammell>Where can people follow you?

01:11:20.160 --> 01:11:21.580
<v Dave Jones>Are you madly online?

01:11:21.780 --> 01:11:22.440
<v Dave Jones>You do the Twitters?

01:11:22.460 --> 01:11:25.280
<v Chris Gammell>I do have a website and a bit of a YouTube channel.

01:11:25.400 --> 01:11:30.860
<v Chris Gammell>But if you want to chat palons or ask any further questions, you know, that post I put up on your blog.

01:11:30.860 --> 01:11:31.380
<v Dave Jones>The forum.

01:11:31.540 --> 01:11:31.780
<v Dave Jones>Yes.

01:11:31.820 --> 01:11:34.400
<v Dave Jones>You put an awesome post up on the EV blog forum.

01:11:34.460 --> 01:11:35.080
<v Dave Jones>I'll link it in.

01:11:35.260 --> 01:11:39.440
<v Dave Jones>That's where you offered to get a whole bunch of detail in there.

01:11:39.440 --> 01:11:40.500
<v Dave Jones>Yeah, it's just people who've got questions about how it works.

01:11:40.500 --> 01:11:41.060
<v Dave Jones>And offered if people have questions.

01:11:41.480 --> 01:11:41.580
<v Dave Jones>Yeah.

01:11:41.580 --> 01:11:42.080
<v Dave Jones>Yeah, sure.

01:11:42.420 --> 01:11:43.800
<v Dave Jones>Yeah, we'll definitely link that one in.

01:11:44.420 --> 01:11:44.780
<v Dave Jones>Awesome.

01:11:44.780 --> 01:11:45.540
<v Dave Jones>Thanks, Toby.

01:11:45.600 --> 01:11:47.520
<v Dave Jones>We'll have to catch up again in person soon.

01:11:47.920 --> 01:11:48.100
<v Dave Jones>Yep.

01:11:48.400 --> 01:11:48.560
<v Dave Jones>Yep.

01:11:48.820 --> 01:11:49.120
<v Dave Jones>Great.

01:11:49.220 --> 01:11:49.400
<v Dave Jones>Cool.

01:11:49.600 --> 01:11:50.000
<v Dave Jones>Thanks, mate.

01:11:50.320 --> 01:11:50.900
<v Dave Jones>Catch you next time.

01:11:50.920 --> 01:11:50.580
<v Speaker ?>All right.

01:11:50.580 --> 01:11:51.100
<v Chris Gammell>Cheers, mate.

01:11:51.200 --> 01:11:51.400
<v Chris Gammell>Bye.

01:11:51.400 --> 01:11:51.400
<v Speaker ?>

01:11:51.400 --> 01:11:51.460
<v Chris Gammell>Bye.

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:11:51.460 --> 01:11:51.460
<v Speaker ?>

01:12:14.780 --> 01:12:23.700
<v Speaker ?>Bye.

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:23.700
<v Speaker ?>

01:12:23.700 --> 01:12:53.680
<v Speaker ?>Thank you.